Test Running
-21 -
Test Running
6. Test Running
6.1 Final Installation Check
Inspect the installation work according to all documents and drawings. Installation Work Check List shows the
minimum check points.
Installation Work Check List
INSTALLATION WORK CHECK LIST
1. Is the unit solidly mounted and leveled?
2. Is the installation location adequate?
Space for the Unit Air Flow
Space for Maintenance Work
Noise and Vibration
Sunshine and Rainfall
Appearance
3. Is the refrigerant piping system adequate?
Piping Size
Cleaning
Length
Dehydration
Bend Air Purge
Insulation Refrigerant Charge
4
.
Is the electrical wiring system adequate?
Wire Size
Tightened Connection
Switch Size
Operation Control Devices
Fuse Size
Safety Devices
Voltage
Hz
5.
Are the stop valves for suction gas and liquid open?
6.
Have the packing glands and the cap nuts for the stop valves been tightened?
6.2 Preparation
Tools and Instruments - High and Low Pressure Compound Gauge(s), Electrical Tester, General Tools
Confirm the system switch is at the OFF position.
6.3 Test Running
When the unit is wired according to the standard label, test running should be performed as follows.
(1) Confirm the system switch is at OFF position.
(2) Check to ensure that the electrical resistance is more than 1 mega ohm by measuring the resistance between
earth and the terminal of the electric parts. If not, do not try to operate the unit until the electrical leakage is
found and repaired.
(3) Ensure that the stop valves of the outdoor unit are fully open, and then start the unit.
(4) Check the room temperature if it is higher than 21
o
C DB and 15
o
C WB while on cooling operation.
(5) Switch ON the main power source.
(6) Check the operating voltage, phase balance and operating current.
(7) Check to ensure that the operate panel functions properly.
(8) Check to ensure that the control and protective devices functions properly (refer to Test Running and
Maintenance Record).