The debugging
☞
Hydraulic station to fill the tank pressurized oil N32 or N46
☞
To move the start button, so that the runway frame rise, removal of the support frame.
Special attention to the first jog observe whether rope in the embrace of a round tank,
location to be correct. (Figure 4)
☞
Pull the handle valve A8 in the unlocking state to observe the safety hook 48 ability to
effectively disengage the insurance piece square hole 9 .
☞
Down the runway rack to lowest position, adjust the nuts on the four wire rope, so that
tension is the same.
☞
Adjust the level of the runway: press the start button, the runway frame up by the
appropriate location, drop the runway according to decline in valve on the hydraulic station.
Make the safety hook into the safety hole. Level detection level of the runway,to be
adjusted with reference to the installation Step 10.
☞
No-load test up and down twice, check each part is working properly. Runway
lock reliability checks, and more repeated several times re-planted on the car to
check the hydraulic system is working properly.
Summary of Contents for YL-3600-H
Page 1: ...1 YL 3600 H Installation Operation Manual ...
Page 10: ...10 Parts of the device exploded view and schedule In millimeters Figure 1 ...
Page 11: ...11 Figure 2 ...
Page 12: ...12 Figure 3 ...
Page 13: ...13 Figure 4 ...
Page 14: ...14 Figure 5 ...
Page 15: ...15 Figure 6 ...
Page 16: ...16 Figure 7 ...
Page 17: ...17 Figure 8 ...