Step 4.Booster Commissioning
Overview:
The booster has an intelligent startup system, booster commissioning is
an automatic process able to guarantee system optimal performance.
As soon as you finish booster system installation, plug it in a power supply to power
on the booster. It will start working and checking the receiving signal and the
isolation to ensure best system performance. Automatic adjustment will take
about 3-5 seconds.
After the booster starts, check whether the coverage is improved or not. If it is
good, the booster commissioning is completed.
You can check the output power displayed on LCD. It may range within
1-3dBdifference which is normal due to outdoor signal conditions. It’s perfect if the
output power reaches its maximum rated value for largest coverage; but you can
always leave it as it is if the coverage is good enough for you.
In case the coverage is not enough, please take measures stated below on the
following conditions.
20