background image

www.hi-velocity.com

© 1995-2020 Energy Saving Products Ltd.

© 1995-2020 Energy Saving Products Ltd.

Pipe Sizing

When sizing refrigerant piping, 

follow the outdoor unit 

manufacturer’s recommendations.

Run the pipes in the most direct route possible, taking into 

account structural integrity and building details. If the evaporator 

is located above the condenser, slope any horizontal runs toward 

the condenser. If the condenser is located above the evaporator, 

a P-trap must be installed at the bottom of the vertical riser. For 

long vertical risers, additional P-traps must be installed for every 

twenty feet (6m). For lines running over 50’ (15m), a suction line 

accumulator must be installed. Lines running over 100’ (30m) are 

not recommended. All lines should be piped so as not to restrict 

access to the front panels, filter section, or electrical enclosure.

Piping the RPM-E

Only  refrigerant  grade  pipe  and  fittings  are  to  be  used  with 

Hi-Velocity Systems. Plumbing fittings may contain wax or other 

contaminants which are detrimental to the proper operation of 

the system. Insulate the suction line with 3/8” (9.53mm) insulation 

such  as  Armaflex.  In  high  heat  areas,  1/2”  (12.7mm)  insulation 

may be needed. If the lines are run in an area where temperatures 

could exceed 120°F (49°C) or runs longer than 50’ (15.24m), then 

the liquid line may need to be insulated as well. Support the pipe 

every 5 feet (1.52m), or whatever local code states.

Brazing & Pressure Testing

The RPM-E comes pre-piped with the coil assembly.  With the 

RPM-E, the Liquid and Suction lines are the only brazing that need 

to be done at the fan coil.  For charging and brazing, remove the 

front access panel of the RPM-E (Fig. RPM-06).  With the access 

panel removed, the coil assembly will be accessible.  Wet rag the 

liquid and suction line (or use a heat dissipating paste) to ensure 

no overheating occurs to the pre-piped coil assembly. Excess heat 

may damage the RPM-E components.

Fig. RPM-06 - Remove Front Access Panel

Once the system has been brazed it must be pressure tested. 

Pressure testing must be done with nitrogen and not refrigerant. 

Typically, pressures are tested to the maximum operating pressure 

that the system will see. Allow the system to hold the nitrogen 

charge for at least 15 minutes to ensure there are no leaks. Check 

with local codes for proper testing procedures. 

After the piping is installed and all components have been 

brazed together, a vacuum pump must be used to evacuate the 

system from both the low and high side to 1500 microns (200 

pa). Add pressure to the system to bring the pressure above zero 

psig. After allowing the refrigerant to absorb moisture, repeat the 

above procedure. Evacuate the system to 500 microns (67 pa) on 

the second evacuation, and ensure that the system holds at the 

vacuum pressure. If not, check for leaks and evacuate again.  At 

this point open service valves on pre-charged condensing units, 

and add refrigerant to the system if necessary.   

Evacuating

The use of an electronic leak detector is recommended, as it is 

more sensitive to small leaks under the low pressures.

Once the system has been determined clean and ready for 

charging,  refrigerant  can  be  added.  The  service  valves  on  the 

condenser  must  be  open  at  this  point.  Never  leave  the  system 

unattended  when  charging.  With  the  system  running,  slowly 

add refrigerant. The typical operating point of an RPM-E coil is 

that of a saturated suction temperature of 38-40°F (3-4°C) and a 

suction line temperature of 42-44°F (6-7°C). In order to prevent 

overcharging during this stage, refrigerant should be added in 

steps.  This  will  allow  time  for  the  system  to  settle  and  prevent 

‘overshooting’  the  ideal  charge.  Condenser  pressures  and 

temperatures remain similar to those in a conventional forced air 

system.  It is recommended that the coil be charged on a high load 

day at the compressor’s highest speed.

Charging

-4-

-4-

Most system start ups require only an adjustment to the 

refrigerant  level  of  the  system.  Should  further  refinement  be 

required,  the  TXV  may  be  adjusted.  A  clockwise  turn  of  the 

superheat valve (the direction in which the cap is screwed on) will 

result in a closing of the valve while a counterclockwise turn (the 

direction in which the cap was unscrewed) will result in opening 

of the valve. Always note system conditions before adjusting the 

valve and allow 5 minutes for the system to settle before making 

any  further  adjustments.  Never  adjust  the  TXV  more  than  one 

quarter turn at a time.

Module RPM-E

Refrigerant Module Installation

Summary of Contents for RPM-E

Page 1: ...y Module RPM E Refrigerant Module Installation 052020 Module RPM E Refrigerant Module Installation 052020 RPM E Refrigerant Module Installation Manual Small Duct High Velocity Heating Cooling and Home Comfort Systems ...

Page 2: ...g connections to the condenser lines quick and easy Fig RPM 01 RPM E Cooling Module Configurations When installing follow the recommendations shown in Table 01 demonstrated in Fig 01 For example a horizontal application could use A to B while highboy applications could use A to B1 Do not use a combination of A to A1 or B to B1 as this would bypass the cooling coil completely A1 is not to be used f...

Page 3: ...is is where the top most extent of the cooling coil is located See Specification Pages for the dimensions of the fan coil units and cooling modules Fig RPM 05 Secondary drain pan Capped Cleanout P Trap Secondary Drain Primary Drain Drain Connections P Trap Secondary Drain Pan The primary condensate drain must have a minimum 3 P Trap installed Fig 05 The drain line must run at a slope of per foot i...

Page 4: ...ure that the system will see Allow the system to hold the nitrogen charge for at least 15 minutes to ensure there are no leaks Check with local codes for proper testing procedures After the piping is installed and all components have been brazed together a vacuum pump must be used to evacuate the system from both the low and high side to 1500 microns 200 pa Add pressure to the system to bring the ...

Page 5: ...quid pressures while closing the valve will decrease suction pressures and raise liquid pressures Bi Flow Receiver The Bi Flow Receiver is designed for use with heat pump systems up to 5 tons and with any typical refrigerants The receiver allows refrigerant a location to migrate to during the heating cycle minimizing head pressures During cooling mode the receiver is empty allowing the full refrig...

Page 6: ...ure that the proper amount of airflow is provided to the coil Check for proper air flows and return air practices Improperly charged systems run the risk of short cycling as well An undercharged system will react much the same as a system with low airflow If the charge is low enough it may trip out on low pressure If a system is overcharged it may trip out on high head pressure Ensure that the sys...

Page 7: ...other products or materials furnished by the installer TERMS CONDITIONS Any repair performed under warranty must be approved by Energy Saving Products Ltd for this warranty to be valid This warranty replaces all other warranties expressed or implied www hi velocity com Should there be multiple consecutive failures of a single part warranty will not be considered unless a contractor has contacted E...

Page 8: ...b Energy Saving Products prides itself on Customer Service and provides design services and contractor support For all of your Heating Cooling and Indoor Air Quality needs the Hi Velocity System is the right choice for you Phone 780 453 2093 Fax 780 453 1932 Toll Free 1 888 652 2219 www hi velocity com Hi Velocity HE Z Fan Coils Hi Velocity HE Z Fan Coils Green Green Technology Technology Build Sm...

Reviews: