Agile Wall
Assembly Instructions
1BVDJ2 rev A
3
Step 1: Frame to base connection
1.1 Set the frame assembly on to the base assembly and secure
with (4) M8 Machine screws per side.
20
.5N
m or S+1
/2
6
Step 2.1: Install tiles on one side of the frame
2.1.1 All tile types (fabric and markerboard) install on to the frame
the same way. Starting with the lower tile, hold the tile flat against
the face of the frame so that the hook rails on the back of the tiles
are just above the horizontal rails in the frame, then let the tile drop
down so that the hook rail on the tiles engages with the horizontal
rail on the frame.
Note
: The lower tile must be installed first before the upper tile can
be installed.
Step3:
3.1 If a markerboard tile is being installed, the marker tray must
be installed to the markerboard tile before installing it on the frame.
Align the flange of the tray with the pre-drilled holes on the back
side of the markerboard tile and install the self tapping screws.
Note:
Be careful not to over tighten the screws.
Note:
Install the center screw first to locate tray left right.
Step 2.2:
2.2.1 Remove the thumb screws from the top channel on top of the
frame. Remove the top channel by sliding the channel over and then
lifting it up and install the tiles.