OWNER/OPERATOR RESPONSIBILITY
It is the owner/operator responsibility to properly use and maintain this equipment.
The instructions and warnings contained in this manual shall be read and understood by the owner/operator prior
to operating this equipment.
If an owner/operator does not understand English, the contents of this manual shall be explained in the owner/
operator native language to assure the owner/operator comprehends.
It is the owner/operator responsibility to maintain the legibility of all warning and Instruction labels.
The owner/operator shall retain this manual for future reference to Important warnings, operating and maintenance
instructions.
INSTALLATION
Installation consists of anchoring the unit
to the floor, connecting an external air
supply with 100 to 120 p.s.i. and routing
the waste oil drain to a suitable waste oil
reservoir.
DO NOT attempt to operate the unit while
on a skid. The initial crush of the oil
filter(s) will cause the unit to move or jump
if not secured properly. The crusher must be
anchored to the floor before operating.
The unit is equipped with a 125 p.s.i. relief
valve that will bleed off air if the unit is
inadvertently connected to an air source
greater than 125 p.s.i.
Install the crusher as follows (See Figure 1).
A. Anchor the unit to the floor using
1/2" diameter hardware.
B. Connect the supplied pressure
regulator/filter to the crusher 3/8"
NPT air inlet fitting.
C. Connect the external air supply to
the pressure regulator/filter.
D. Place a waste oil collection
receptacle underneath the waste
oil port.
Figure 1
1/2" Floor anchor
Filter/Regulator
Waste oil
drain fitting
3/8 NPT Air Inlet
Page 4 of 8