FIGURE 19.  Hole and New Framing Members

If the area above the ceiling is 

NOT

 an attic, position

and secure the ceiling firestop on the ceiling side of
the previously cut and framed hole.

FIGURE 20.  Ceiling Firestop (Ceiling Side)

If the area above the ceiling 

IS

 an attic, position and

secure the firestop on top of the previously framed hole.

C. Flue Termination

For Horizontal Terminations -

 To attach and secure

the termination to the last section of horizontal flue:

The rear flue heat shield MUST be placed one inch
above the top of the flue between the wall shield and
the base of the termination cap.

One section of the heat shield is attached to the wall
shield. The other is attached to the termination cap
in the same manner.

The heat shield sections will overlap to match the
wall thickness (depth). The small leg in the shield
rests on top of the flue to properly space it from the
pipe section (see Figure 22).

JOIST

CEILING FIRESTOP

CEILING

NAILS (4 REQUIRED)

CEILING

CEILING FIRESTOP

RAFTER

NAILS (4 REQUIRED)

CEILING

NEW
FRAMING
MEMBERS

EXISTING CEILING 
JOISTS

CHIMNEY
HOLE

10" (254mm)
 

10” (254mm) 

FIGURE 22. Flueing through the Wall

EXTERIOR

INTERIOR

Interior 

Wall Shield

Inner Flue

Rear Vent 

Heat Shield 

38mm min. 

overlap

Outer Flue

38mm min. 

Overlap

FIGURE 21.    Attic Firestop

The termination kit should pass through the wall
firestops from the exterior of the building.

Adjust the termination cap to its final exterior posi-
tion on the building and interlock the flue sections.

WARNING: THE TERMINATION CAP
MUST BE POSITIONED SO THAT THE
ARROW IS POINTING UP.

Use a high-temperature sealant gasket to seal be-
tween the pipe and exterior firestop.

Summary of Contents for 6000TRS-AUB

Page 1: ...044 USA 1 888 427 3973 2022 900F 7 04 INSTALLATION AND OPERATION INSTRUCTIONS This product is covered by one or more of the following patents United States 4 112 913 4 408 594 4 422 426 4 424 792 4 52...

Page 2: ...ual Report to your dealer any parts dam aged in shipment specifically check glass condi tion The gas logs and flue system components are in separate packages Read all instructions before INSTALLATION...

Page 3: ...staller Testing 21 2 0 OPERATING INSTRUCTIONS 21 2 1 Safety and Lighting Information 23 2 2 Safety Information 23 2 3 Lighting Instructions 24 2 4 Fan Operation 25 3 0 SERVICING AND MAINTENANCE 25 3 1...

Page 4: ...r remote control are desired If the heater is to be installed on carpeting or tile or on any combustible material other than wood flooring the heater should be installed on a metal or wood panel that...

Page 5: ...Locating the Heater The diagram See figure 2 shows space and clearance requirements for locating a heater within a room Minimum Clearances from the Heater to Combustible Materials Glass Back of Sides...

Page 6: ...ERIFY FRAMING METHODS AND WALL COVER ING DETAILS BEFORE FRAMING CONSTRUCTION BEGINS NOTE Dimension B taken from finished hearth frame Dimensions D and E taken from bottom of unit For minimum clearance...

Page 7: ...input 300 Appliances over 50 MJ h input 500 b From the ground or above a balcony 300 c From a return wall or external corner 500 d From a gas meter M 1000 e From an electricity meter or fuse box P 50...

Page 8: ...are listed as TOTAL MAXIMUM verti cal dimensions FIGURE 5 V CAP V MAX RUN 36 FT 10 9m FIGURE 4 1 3 FLUE SYSTEM APPROVALS AND INSTALLA TIONS This model is approved to use DVP Series flue pipe component...

Page 9: ...M V FT H FT 1 MIN 305mm 4 MAX 1 22m 2 MIN 610mm 8 MAX 2 4m 3 MIN 914mm 12 MAX 3 7m 4 MIN 1 22m 16 MAX 4 9m V H 24 MAX 7 3m H 8 MAX 2 4m FIGURE 8 Flueing with One 90 Elbow NOTE If a 90o elbow is first...

Page 10: ...3 MIN 914mm 4 MAX 1 22m 12 MAX 3 72m 4 MIN 1 22m 6 MAX 1 8m 16 MAX 4 9m 20 MAX 6 1m 6 MAX 1 8m 16 MAX 4 9m FIGURE 10 Flueing with Two 90 Elbows V FT H H1 FT 1 MIN 305mm 4 MAX 1 22m 2 MIN 610mm 8 MAX 2...

Page 11: ...3 6 m 4 MIN 1 22 m 8 MAX 2 48 m 16 MAX 4 9 m 8 MAX 2 48 m 16 MAX 4 9 m NOTE V V MAX 36 10 9 m FLUEING WITH THREE 3 90 ELBOWS FIGURE 11 Flueing with three 90 elbows V H H H1 H2 1 MIN 305 mm 2 MAX 610...

Page 12: ...914mm 12 MAX 3 7m 4 MIN 1 22m 16 MAX 4 9m NOTE H H1 16 MAX 4 9m V V1 H H1 36 MAX 10 9m V FT H H1 FT 1 MIN 305mm 4 MAX 1 22m 2 MIN 610mm 8 MAX 2 4m 3 MIN 914mm 12 MAX 3 7m 4 MIN 1 22m 16 MAX 4 9m H H1...

Page 13: ...ling Flue Components After determining which set of starting collars will be used top or rear follow flueing instructions accordingly Flueing Out the Rear Flue Remove the installed rear seal cap from...

Page 14: ...pre viously cut and secure the firestops with nails or screws The pipe opening of the firestops MUST BE placed towards the bottom of the firestop Continue the flue run through the firestop FIGURE 18...

Page 15: ...me manner The heat shield sections will overlap to match the wall thickness depth The small leg in the shield rests on top of the flue to properly space it from the pipe section see Figure 22 JOIST CE...

Page 16: ...ical flue pipe to combus tible materials Mark the roof hole accordingly Cover the opening of the installed flue pipes Cut and frame the roof hole Use framing lumber the same size as the roof rafters a...

Page 17: ...E BRN BR N BLUE GRD BLUE JUNCTION BOX DETAIL FAN TEMPERATURE SENSOR SWITCH FAN SPEED CONTROL JUNCTION BOX 1 5 FAN These heaters have a factory installed Fan Electrical Junction Boxes variable speed Rh...

Page 18: ...SEALED A 150 C MINIMUM SEALANT MATERIAL MUST BE USED THESE JOINTS ARE NOT REQUIRED TO BE SEALED ONLY NON COMBUSTIBLE MATERIAL USING 150 C MINIMUM ADHESIVE IF NEEDED CAN BE APPLIED A S FACING TO THE F...

Page 19: ...cate log 1 on grate with notches and push log against rear log locators LOG 2 SRV382 702 Locate log 2 on grate with notches Slide left end of log forward and right side back against tab Log Assembly L...

Page 20: ...the right end on top of log 2 LOG 5 SRV382 705 Place bottom of log 5 between the 4th and 5th grate bars and rest the top onto log 1 LOG 6 SRV438 724 Place the Y shaped part of log 6 over the 3rd grate...

Page 21: ...he building WARNING THIS UNIT IS NOT FOR USE WITH SOLID FUEL The control system for this model is a millivolt type It consists of a gas control valve variable regulator a stand ing pilot assembly a th...

Page 22: ...E THE UNIT CAN BE PLACED INTO SAFE OP ERATION DO NOT USE THIS APPLIANCE IF ANY PART HAS BEEN UNDER WATER IMMEDIATELY CALL A QUALIFIED SERVICE TECHNICIAN TO INSPECT THE UNIT AND TO REPLACE ANY PART OF...

Page 23: ...has been under water Immediately call a qualified service technician to inspect the appliance and to replace any part of the gas control system which has been under water 2 1 SAFETY LIGHTING INFORMATI...

Page 24: ...houldnotrequireaccessingforlighting purposes The pilot is located inside the combustion chamber THERMOPILE PILOT BURNER 6 To put the control in the pilot position turn the control knob counter clockwi...

Page 25: ...sh ing at least twice a year CAUTION THE LOGS GET VERY HOT HANDLE ONLY WHEN COOL WARNING DO NOT USE ABRASIVE CLEANERS ON THE GLASS DOOR ASSEMBLY DO NOT ATTEMPT TO CLEAN THE GLASS DOOR WHEN IT IS HOT F...

Page 26: ...m the underside of the thermopile The thermopile can then be sepa rated from the pilot bracket Unscrew the pilot assembly bracket and remove NOTE When removing the pilot assembly carefully pull the el...

Page 27: ...gnitor 1 Using a match light pilot If pi lot lights turn off pilot and trig ger the red or black button again If pilot lights an improper gas air mixture caused the bad light ing and a longer purge pe...

Page 28: ...micro switch and connect to terminal TP on the gas valve Turn green knob to pilot position depress and light pilot light If meter reading is greater than 325 m v after 30 seconds the pilot generator i...

Page 29: ...allow for igni tion or the heater continues to shut off disconnect the limit switch wire from the gas valve and repeat the lighting instruc tions If the pilot and burner re main lit after the heater...

Page 30: ...debris or blockage 1 Adjust the log set so that the flame does not impinge on it 1 Adjust the air shutter at the base of the burner 1 Inspect the opening at the base of the burner It is imperative th...

Page 31: ...31 6000TRS AUB Exploded Parts Diagram 4 0 Replacement Parts Service Parts List on following page 21 Log set assembly 27 24 26 25 22 23 5 16 17 2 1 19 20 3 15 14 13 12 18 4 7 6 8 11 9 10 29 28 30 31...

Page 32: ...9 13 Blower Assembly 240v 100 505A 14 Junction Box 546 250A 15 Cord 546 251A 16 Pilot Assembly NG 530 510A Pilot Assembly LP 530 511A 17 ON OFF Rocker Switch 060 511 18 Heat Shield Baffle 2022 100 19...

Page 33: ...t the current wholesale price defective electrical or manual components optional components or accessories and glass panels not including glass panels broken during misuse or careless handling HEAT N...

Reviews: