Harnois ABRI SPA Assembly Instructions Manual Download Page 15

    

 

 

 

 

SPA ENCLOSURE 

 
 

 

5

1.

 

Assemble the 4 caster wagons accord ing to the illustrations (Fig.AA, 

DD,EE) and bolt them loosely. 

Note:

 the parts of material with Velcro 

that are fixed under the caster wa gons are attached to the fabr ics 

of the movable sections 

2.

 

Assemble the arches of the mov able structures on the ground,  as  

illustrated on page SPA-400 

3.

 

With the assistance of another person, slip the structures by the front 

and back end of the pr incipal structure, taking care not to r ub the 

fabric of the principal structure with the caster wagons 

4.

 

Adjust or slip the wheeled bracket under the rails 

5.

 

Firmly tighten the bolts of the caster wagons  

 

Step 6: Installation of the fabrics on the two sections of movable roof 

 

1.

 

Slip the  fabri c by th e side.  Attach the Velcro ba nds of th e fabr ic 

below the wagon on each side (Fig.FF) 

2.

 

Very important:

 in order to make sure that the fabric is well centered 

and on the r ight side of the mov able structure, fix the eyel et that is 

in the center of the fabric so it is at the ridge of the arch towards the 

center of the shelter,  then i nsert the eyelet i nto the bolt of part #3  

(Fig.CC) 

3.

 

Fold up the fabr ic towards the i nterior of the arch and begi n lacing 

with the c ord, starting on one si de towards the opposi te side, using 

the doubled method (F ig.GG, Y), without however putting the f inal 

tension 

4.

 

Use of retaining straps (Fig.HH) 

Summary of Contents for ABRI SPA

Page 1: ...de la stru cture principale et les coins d arches 38 des structures m obiles sont pratiquem ent identiques Ils ne peuvent tre invers s lors de l assemblage Donc a ssurez vous qu ils soient fix s la bo...

Page 2: ...z l querre qui sert d ancrage au bas des arches 15 Fig F G I K 3 Soulevez la prem i re arche et boulonnez les diagonales 5 aux poteaux de la premi re arche Fig L 4 Soulevez la deuxi m e arche Fig T et...

Page 3: ...11 Fig R Installez les 4 supports d e porte 27 aux illets de la partie sup rieu re de la porte et dans la pi ce 11 de la structure principale Fig R 5 Ajustez la largeur la base de la struct ure 144 e...

Page 4: ...boulonner que tr s l g rem ent Note les pi ces de m at riel avec Velcro 40 qui sont fix es en dessous des chariots sont attach es aux toiles des sections mobiles Assemblez les arches des structures m...

Page 5: ...ers le c t oppos en utilisant la m thode doubl e Fig GG Y sans tou tefois mettre la tens ion finale V rifiez ce que la toile au toit soit ajust e sans plis r ajustez les bandes de Velcro sous les char...

Page 6: ......

Page 7: ......

Page 8: ......

Page 9: ......

Page 10: ......

Page 11: ...ther the parts together in groups according to the illustrations on page SPA 900 2 Important The corner arches 3 of the pri ncipal structure and the corner arches 38 of the mov able structures are pra...

Page 12: ...holes and the posts 9 for the half arch i n the center Important put the end w ith the guard towards the top Fig A 2 Join the bottom of the posts of the first arch with the bottom of the posts of the...

Page 13: ...wards the back of the shelter Handle the fabric with care Fig N 2 Center the fabr ic on the structure without lacing it To know i f the fabric is w ell centered on the structure the d istances between...

Page 14: ...9 Begin lac ing w ith the cord beginning on one si de towards the opposite side usi ng the doubled method F ig Y wi thout howe ver putting final tension Make sure that the fabric on the roof is adjust...

Page 15: ...the rails 5 Firmly tighten the bolts of the caster wagons Step 6 Installation of the fabrics on the two sections of movable roof 1 Slip the fabri c by th e side Attach the Velcro ba nds of th e fabr i...