9.3 Disassembly procedure
NOTE!
In case of doubt, to identify the various parts refer to the exploded view at the end of this
manual.
NOTE!
The disassembly procedure is useful for the maintenance, cleaning and lubrification of every
item of the product.
In the procedure, three types of operations are described:
- Flush deck operations
- Under deck operations
- Bench operations: for all operations for which user must have a comfortable position to
disassemble and reassemble the several components. For those operations, is strongly
recommended to operate on a proper bench to avoid damages and to operate into the correct
rooms dedicated for the tooling handling.
1. Remove the fiber optics: from the open drum configuration, disconnect the fiber optics following the
opposite order of the procedure specificed in the section #16.4 of this manual (Led lights installation).
Only in case the fiber optics are broken or damaged, proceed with the substitution of the led kit, with
the removal and the installation (for the spare kits and parts see section Ordering spare parts of this
manual).
2. Flush deck operation - Place the drum support to keep open the drum:
Tools needed:
- One number 5 allen wrench
- One number 13 adjustable spanner
- One number 10 adjustable spanner
- Rags
Torque to apply in assembly phase