Hammar ERRS CP2 Installation And Test Download Page 5

Instruction for connecting the cable screen in the EMC cable glands 

 

Strip the cable and cut the screen to approximately 3 cm. Fold back the screen before inserting 

the cable into the cable gland. Insert the cable into the cable gland until the screen gets in line 

with the inner end of the cable gland. This will ensure that the EMC fingers will connect the screen 

to the cable gland when the cable gland nut is tightened. 

 

 

 

ERRS CP2 Control Panel

 

 

See the ERRS CP2 wiring diagram for the connections inside of the ERRS CP2 control panel. 

The terminals inside the ERRS CP2 enclosure is of spring-loaded type. Inset a small screwdriver 

in the slot beneath the opening for the wire and bend gently downwards to open the terminal to 

insert the wire. The maximum wire area for the terminals inside the ERRS CP2 enclosure is 2,5 

mm

2

 

Emergency power 

 

Emergency power shall be connected to all ERRS Control Panels. The voltage level must be within 

the range 16 - 36 V DC 

The maximum current consumption for the system is 0,5 A. Internal fuses S1 – 1.0AF 5x20 mm 

glass tube fuse. 

See wiring diagram for maximum cable length and area. 

 

H20 ERU 

 

Cut the flexible cable of the H20 ERU to a sufficient length and fix it so that it as far as possible is 

protected against mechanical damage. Before the H20 ERU is connected to the connecter box 

the ERRS CP2 installation must be tested. Finally, when connecting the H20 ERU to the connector 

box, polarity does not matter. 

 

External alarm 

 

The ERRS CP2 control system shall be connected to the ships general alarm system. The external 

alarm function is an isolated normally closed contact (when system is ok). When an alarm occurs, 

the contact will open and remain open until the cause for the alarm is sorted out. Maximum 1,0 

A and 24VDC 

 

Control panel addressing 

 

When more than one control panel is connected in a network each control panel has to have a 

unique address. The address is set on the rotating switch on the connector board in the ERRS CP2 

enclosure. The address is set by HAMMAR at the configuration of the systems before delivery. 

Make sure that each control panel is mounted at its specified location. 

 

 

Summary of Contents for ERRS CP2

Page 1: ...and use of the ERRS system Note After the battery has been connected to the system it will automatically take over the power supply to the ERRS CP2 system if the ships emergency power supply is switc...

Page 2: ...rder to avoid water or dirt to get inside the box When the installation is finished all holes in the ERRS CP2 enclosure shall have EMC cable glands or sealing plugs installed There shall be no opening...

Page 3: ...tion so that it is ensured that the connection cable of the H20 ERU can be connected Mount the connector box with the cable glands in a horizontal position and in a protected position with respect to...

Page 4: ...ERRS CP2 enclosure Only use the original type of cable glands Additional cable glands can be ordered from CM HAMMAR AB The Enclosure shall be connected to ships ground by the Ground connection device...

Page 5: ...imum current consumption for the system is 0 5 A Internal fuses S1 1 0AF 5x20 mm glass tube fuse See wiring diagram for maximum cable length and area H20 ERU Cut the flexible cable of the H20 ERU to a...

Page 6: ...ep 7 and 8 for all outputs to ensure that all outputs are connected to the right release unit 10 When all outputs have been checked push the MAINTENANCE pushbutton to exit the maintenance menu Activat...

Page 7: ...inputs activates the correct outputs or sequence of outputs Testing activation by the use of fuses Connect a fuse between the terminals in ERU connection box for the output to be tested Connect jumpe...

Reviews: