1

.  Wall

 

should already be framed for the fountain

 using the positioning dimensions shown in Figure 3. Shown

    dimensions pertain to installation location (framing must support up to 300 lbs. weight).  These dimensions

     are required for compliance with ANSI Standard A117.0.

2.  Attach wall plate assembly to wall

 as shown in Figure 3 using 5/16" x 2" long bolts and flat washers

     (not provided). Tighten securely. (Fastener must match wall type, i.e. lag screws for wood studs, bolts and

     anchors for masonary construction.)

3.  Install back panel.

 Place the upper edge of the panel above hanger on the wall. Slide panel down until it

     engages the hanger. Be sure back panel is firmly engaged before releasing it.

4.  Install rough-in plumbing

 as shown in Figure 3. Waste line should extend a minimum of 2" (51mm) thru the

     back panel. Run supply water inlet line thru back panel. Install a service stop (not provided). Turn on supply

      water and flush thoroughly.

5.  Remove bottom access panel

 from fountain basin and save the screws. Install the fountain to the back

     panel using (4) 5/16" x 3/4" long screws and washers (provided) thru holes in back panel. Tighten securely.

6.  Cut waste tube

 to required length using plumbing hardware and a trap (not provided) as a guide. Install

      hardware and trap. Tighten securely.

7.  Make water supply

 connections from service stop to the 3/8" O.D. unplated copper tube coming out of the

     fountain strainer (See Fig. 1). Turn on water supply and check for leaks. Newly installed water supply line

      should be insulated after leak check is completed. 

DO NOT SOLDER TUBES INSERTED INTO THE STRAINER

      AS DAMAGE TO THE O-RINGS MAY RESULT.

8.  These products are designed

 to operate on 20-105 PSIG supply line pressure. If inlet pressure is above

     105 PSIG, a pressure regulator must be installed in the supply line. Any damage caused by reason of

      connecting these products to supply line pressure lower than 20 PSIG or higher than 105 PSIG is not

       covered by warranty.

9.  Check stream height from bubbler

. Stream height is factory set at 45-50 PSI. If supply pressure varies

     greatly from this, remove items 3 and 4 and adjust screw on regulator (Item 9). Clockwise adjustment

     will raise stream height and counter-clockwise adjustment will lower stream height. For best adjustment

     stream height should be approximately 1-1/2" (38mm) above the bubbler guard. (See Fig. 6)

10. Replace bottom access

 panel to fountain basin using screws provided. Tighten securely.

TROUBLE SHOOTING AND MAINTENANCE

1.  

Orifice Assy:

  Mineral deposits on orifice can cause water flow to spurt or not regulate.  Mineral deposits

     may be removed from orifice with a small round file not over 1/8" diameter or a small diameter wire.

      CAUTION:

  

DO NOT

 file or cut orifice materials.

2.  

Stream Regulator:

  If orifice is clean, regulate flow as in "START UP" instructions above. If replacement is

     necessary, see parts list for correct regulator part number.

3.  

Actuation of Quick Connect Water Fittings:

  Cooler is provided with lead-free connectors which utilize an

     o-ring water seal.  To remove tubing from the fitting, relieve water pressure, push in on the gray collar while

     pulling on the tubing (See Figure 2).  To insert tubing, push tube straight into the fitting until it reaches a

     positive stop, approximately 3/4".

Summary of Contents for HCRF-EBP

Page 1: ...G OR MAY OCCURAWAY FROM THE BUILDING THIS GROUNDING CAN CAUSE ELECTRICAL FEEDBACK INTOAFOUNTAIN CREATINGAN ELECTROLYSIS WHICH CAUSESA METALLIC TASTE ORAN INCREASE IN THE METAL CONTENT OF THE WATER THIS CONDITION ISAVOIDABLE BY USING THE PROPER MATERIALSAS INDICATED ANY DRAIN FITTINGS PROVIDED BY THE INSTALLER SHOULD BE MADE OF PLASTIC TO ELECTRICALLY ISOLATE THE FOUNTAIN FROM THE BUILDING PLUMBING...

Page 2: ... 2 LEGEND A RECOMMENDED WATER SUPPLY LOCATION 3 8 O D UNPLATED COPPER TUBE CONNECT STUBBED 1 1 2 38mm FROM WALL SHUT OFF BY OTHERS B RECOMMENDED LOCATION FOR WASTE OUTLET 1 1 4 O D DRAIN C 1 1 4 DRAIN FURNISHED HCRF EBP ROUGH IN FIG 3 ...

Page 3: ...ne should be insulated after leak check is completed DO NOT SOLDER TUBES INSERTED INTO THE STRAINER AS DAMAGE TO THE O RINGS MAY RESULT 8 These products are designed to operate on 20 105 PSIG supply line pressure If inlet pressure is above 105 PSIG a pressure regulator must be installed in the supply line Any damage caused by reason of connecting these products to supply line pressure lower than 2...

Page 4: ...ting Washer Flat 339 359ID Steel Screw Mach 5 16 18 x 3 4 Set Screw 6 32 X 12 Wrench Allen 40575C 15005C 45662C 45737C 50986C 51544C 100322740560 15008C 61313C 70022C 112627543890 55996C 55001130 55000665 28290C 40045C 28291C 56092C 28286C 45679C 45805C 50074C 62095C 45736C 75541C 111577243890 70023C 75539C 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 NS DESCRIPTION FIG ...