Ober-
seite
Podes
t
HTT-A
-11/06
Ober-
seite
Podest
HTT-A-
11/06
Ober-
seite
Podes
t
HTT-A
-11/06
Ober-
seite
Podes
t
HTT-A-1
1/06
3
© 2018 HALFEN · INST_HTT 01/18 · www.halfen.com
HALFEN HTT
Assembly Instructions
Deutsch
English
Polski
HTT Sound Insulation Element
Pre-cast production
HTPL Joint sheets
to be attached on the side wall following the stairway using the integrated self-adhesive tape. The
joints must be cleaned carefully and carried out without lack! Afterwards they have to be clossed with adhesive tape.
Bottom HTT nailing bar
to be fi xed to the formwork at the appropriate place. Insert HTT Element.
Top HTT nailing bar
to be attached using a fi xing structure (e.g. timber batten
) and placed on the HTT Impact
sound insulation unit from the top. The HTT Element must be aligned and fi xed vertically and at the appropriate positi-
on.
Installation of site reinforcement according to accounts of the structural engineer. Concreting landing and stairway.
Shuttering in the pre-cast plant
Installation on the construction site
6
1
2
3
4
5
5
6