9.2 Functional 

test 

Trolleys 

Carefully move the trolley to the end positions and check the positions of the end stops. 

 

 

10 Maintenance 

 

 

10.1 General 

All monitoring, servicing and maintenance operations are to ensure correct functioning of the equipment; 
they must be effected with utmost care. 

ƒ

  Only “qualified persons” may do this work. 

ƒ

  Servicing and maintenance work must only be done when the hoist is not loaded. 

ƒ

  Records must be kept of all test results and measures taken. 

 

10.2 Monitoring 

The monitoring and servicing intervals stated are valid for operation under normal conditions and single-shift 
operation. In case of severe operating conditions (e.g. frequent operation with full load) or special 
environmental conditions (e.g., heat, dust, etc.), the intervals must be shortened correspondingly  

 

 

11 Inspection 

 

 

11.1 Periodic 

checks 

Independently from the regulations of the individual countries, lifting devices must be checked at least yearly 
by a qualified person or licensed qualified person regarding its functional safety.  

 

 

at 

commissioning 

daily 

checks 

1st maintenance 

after 

3 months 

Inspection 

Maintenance 

every 

3 months 

Inspection 

Maintenance 

every 

12 months 

 

check screw connections 

 

 

 

 

check the bearings 

 

 

 

 

 

check the trolley wheels 

 

 

 

 

 

check lubrication of the driving pinion 

 

 

 

 

buffers - check correct position and wear 

 

 

 

 

electric motor* - check the brake lining 

 

 

 

 

 

electric motor* - check the brake 

 

 

 

 

pneumatic motor* 

 

 

 

Have the equipment checked by an expert 

(periodic inspection) 

 

 

 

 

 

*as far as applicable 

 

12 Service 

 

 

Maintenance must be effected by lubricating the driving pinions (for hand geared trolleys) and by checking 
the rubber end stops. 

 

 

12.1 

Lubricant - Selection 

FUCHS SHELL  ESSO  MOBIL TOTAL  CASTROL 

KLÜBER 

Renolit FEP 2 

Alvania EP 2 

Unirex EP 2 

Mobilux EP 2 

MULTIS EP2 

-- 

-- 

Stabylan 5006 

-- 

-- 

-- 

-- 

Optimol Viscoleb 1500 

Klüberoil 4UH 1-1500 

-- -- -- -- --  -- 

Wolfracoat 

99113 

Chain lubricant OKS 451 

12.2 

Lubricant for food industry – Selection (as option*) 

 

SHELL MOBIL 

CASTROL 

KLÜBER 

Gearing 

FM Grease HD2 

Mobilgrease FM 222 

-- 

Klüberoil 4UH 1-1500 N 

Load chain 

-- 

Lubricant FM 100 

Optimol Viscoleb 1500 

-- 

Load hook; 

Pulleys 

Gear rim;  

Drive pinion 

FM Grease HD2 

Mobilgrease FM 222 

 

-- 

-- 

* must be mentioned by order 
 

 

Summary of Contents for 18/16R-VA

Page 1: ...5 52 122 00 01 02 Rev 02 HADEF Monorail Trolley Type 18 16VA as push travel trolley R as hand geared trolley H Stainless steel design Installation Operating and Maintenance Instructions...

Page 2: ...nges Table of Contents 1 Information 3 2 Safety 3 2 1 Warning notice and symbols 3 2 2 Duty of care of the owner 4 2 3 Requirements for the operating personnel 4 2 4 Appropriate use 5 2 5 Basic safety...

Page 3: ...packed properly Check the goods after receipt for any damage caused during transport Report any damage immediately to the forwarding agent This manual allows a safe and efficiently use of equipment Im...

Page 4: ...lt free fully functional condition and the safety components in particular are checked regularly to ensure that it is functioning properly The required personal protective equipment for the operators...

Page 5: ...re for a free view on the load Only use the hoists appropriately The equipment is to be used exclusively for movement of goods Under no circumstances my persons be moved Never load the devices beyond...

Page 6: ...gainst corrosion 4 Description 4 1 Areas of application The devices must be as far as possible installed in a covered room If they are used in the open protect the units against the effects of weather...

Page 7: ...ion depends on the local environment The hoist must be suspended in a way that it can position itself freely 6 1 Trolley For assembly on a beam a travel limit must be placed at either end of the track...

Page 8: ...the trolley onto the beam flange from below Push the trolley together again until it reaches the correct wheel gauge Secure the washers and distance tubes by tightening the hexagon nuts and the safet...

Page 9: ...is hoists ready for operation acc validated national regulations with EU declaration of conformity Definition qualified person former expert A qualified person has learned due to occupational trainin...

Page 10: ...ified person regarding its functional safety at commissioning daily checks 1st maintenance after 3 months Inspection Maintenance every 3 months Inspection Maintenance every 12 months check screw conne...

Page 11: ...re parts 14 Decommissioning WARNING It is essential that the following points are observed in order to prevent damage to the equipment or critical injury when the device is being decommissioned It is...

Reviews: