Hot Press PM-1606
Author:
S.D.T. / KM
ORDINARY MAINTENANCE
Edition: 02/2005
Page
E-5
Replaces: 01/2002
T
ABLE
17
-
P
ERIODIC MAINTENANCE WORK
Operation Period
Personnel
Method
General cleaning
Daily
Operator
Clean the press after use. Remove dust and any
deposits with a clean cloth without the use of
solvents.
Check water
connections
Daily
Maintenance
worker
Check with your fingers that there are no water
leaks. If the situation is overlooked for some time
there may be calcium deposits visible.
Checking compressed
air connections
Monthly
Maintenance
worker
Listen for any air leaks.
Check all the electrical
cables on the system in
its stationary operation
Monthly
Maintenance
worker
Check for defective insulation or connectors.
Check all the electrical
cables on the system in
its mobile operation
Weekly
Maintenance
worker
Check defective insulation or connectors.
Measurement of heating
plates temperature
Monthly
Maintenance
worker
Position the heat-resistant expanded silicone
rubber pad on the lower heating plate. Close the
press normally. Submit the pressure chamber to a
pressure of maximum 1 bar. Switch the heating
on, set the nominal value at 180°C and switch the
time relay off.
After 40 minutes heating time, open the press,
slightly lift the upper heating plate and insert a
precision thermometer between the expanded
silicone rubber pad and the upper heating plate,
exactly in the center of the heating plate.
Close the hot press (just under its own weight).
Take a temperature reading after about 3 minutes.
Repeat the procedure for the lower heating plate
(insert the sensor under the expanded silicone
rubber pad in the center of the heating plate). The
temperature measured must be at 180 °C +/- 2 °C
(max. measuring pre/- 1°C ).
If the temperature is not yet within the set range it
will be necessary to adjust the temperature offset
in the PMR-XX unit (see its own manual).