Foundation Information
!Attention
Please refer to following details for foundation work.
Base plates are welded to the Rolling Hill’s pipe. After assembling
pipes and nets, fix the structure on the concrete.
Foundation Detail Foundation
Pouring Concrete
Pour concrete* into wooden support frame until flush to top edge
Allow 3-5 days for concrete to cure before proceeding to next step.
*Concrete is to be wet concrete with
minimum 25 MPA / 3500PSI.
**See the drawing
Foundation
Foundation