6. 2.66" Corrugated Commercial Hopper Tank 10-22 Rings
PNEG-1451
Ladder, Safety Cage and Platform for Hopper Tanks
59
Location of Field Drilled Holes for Intermediate Ladder
Starter Brackets
Before installing the starter brackets, field drill two (2) 3/8" holes (A) located 2.66" below and directly in
line with the top horizontal seam holes located in the third ring up from the intermediate platform mounting
angles (B). The first hole, required for the right hand starter bracket, must be located 9-3/8" from the center
of the left hand intermediate platform mounting angle (B) to the center of the hole. The second hole, required
for the left hand bracket, must be located 18-3/4" from the center of the first hole.
proper location of the two (2) 3/8" field drilled holes (A) required to install the starter brackets.
Figure 6T
Ref #
Description
A
Field Drill Two (2) 3/8" Holes
B
Intermediate Platform Mounting Angles (
for proper installation.)
Summary of Contents for PNEG-1451
Page 2: ...2 PNEG 1451 Ladder Safety Cage and Platform for Hopper Tanks...
Page 18: ...18 PNEG 1451 Ladder Safety Cage and Platform for Hopper Tanks NOTES...
Page 40: ...40 PNEG 1451 Ladder Safety Cage and Platform for Hopper Tanks NOTES...
Page 70: ...70 PNEG 1451 Ladder Safety Cage and Platform for Hopper Tanks NOTES...
Page 92: ...92 PNEG 1451 Ladder Safety Cage and Platform for Hopper Tanks NOTES...