GRUNDFOS ALLDOS U 189-010 Technical Information Download Page 8

8

V3.0

U 189-010 en

5.3

First Commissioning

After the leak test has been terminated successfully, the
vacuum change - over device can be commissioned.

1

Entirely open the connecting valves of the drums or
cylinders.

2

Start the injector. Thereafter chlorine gas is dosed. The
position of the indicator pin of the change - over device
signals from which battery the chlorine gas is supplied.

5.4

Checking the Change - Over Function

1

Open all cylinders or drums and start the injector.

2

Close the supply battery that is in operation.

3

The change - over device switches the gas supply over
to the stand - by battery after a short period of time (that
depends on the dosing quantity and the length of the
line).

4

Then check, if the changing over from the stand - by
battery to the former supply battery functions, as well.

5

Open again all cylinders or drums. The vacuum change
- over device is now ready for operation.

5

Commissioning

After having completed the installation continue ommissioning
the change - over device.

WARNING

The device must be commissioned  only by
qualified personnel strictly complying with the
instructions for handling the hazardous sub-
stance chlorine. The qualified staff must wear
protective clothing and gas mask when doing
the work described in the following.

NOTE

Prior to the initial starting all parts carrying
chlorine gas have to be checked for leaks.

5.1

Leak Test of the Vacuum Side

1

Close the connecting valves of the drums or cylinders.

2

Start the injector. Thereupon the vacuum lines are
evacuated and in this operating state the change - over
device switches uncontrollably.

3

After about 10 minutes (depending on the length of the
vacuum lines and on the setting of the adjusting valve)
the rotameter must not indicate a flow.

4

If the rotameter yet indicates a flow, the complete dosing
system must be checked for possible leaks.

Warning

As precondition for the leak test the chlorine
gas dosing unit must be evacuated and free of
chlorine gas and the injector be in operation.

5

To check the single components of the dosing system,
disconnect the vacuum lines between the vacuum regu-
lators and the rotameter one after the other and close
them tight with the finger.

6

If the rotameter stops indicating a flow after having dis-
connected one of the vacuum lines, the leaks has to be
at the disconnected component.

5.2

Leak Test of the Pressure Side

1

Stop the injector.

2

Open the connecting valves of the drums or cylinders by
about one revolution.

3

Check the connecting parts and inlet valves of the
vacuum regulators for leaks by means of ammonia.
Leaks are localized by passing the bottle with ammonia
close by the relevant parts and squeezing a little bit of
ammonia gas out of the bottle. If there is chlorine gas
escaping anywhere, white vapour develops.

WARNING

Even the slightest detected leaks have to be
removed immediately.

Summary of Contents for U 189-010

Page 1: ...1 15 710057 V3 0 U 189 010 en Vacuum Change over Device U 189 010 Technical Information...

Page 2: ...ical Information Version 3 0 Publisher ALLDOS Eichler GmbH Reetzstra e 85 76327 Pfinztal S llingen Postfach 1160 76317 Pfinztal Tel 49 72 40 61 0 Fax 49 72 40 61 211 Mail alldos de alldos com Internet...

Page 3: ...ng commissioning It will help you and your GRUNDFOS Alldos servicing partner to adjust the device during subsequent corrections Owner GRUNDFOS Alldos customer No Contract No Order No of device Serial...

Page 4: ...2 Construction and Function 6 3 Technical Data 6 3 1 Electrical Data of Remote Indicator 6 4 Installation 6 5 Commissioning 8 5 1 Leak Test of the Vacuum Side 8 5 2 Leak Test of the Pressure Side 8 5...

Page 5: ...rms of sale and delivery shall only be valid if the installation is implemented exclu sively by an authorized and suitably qualified personnel The safety instructions and recommendations given in this...

Page 6: ...l2 SO2 Optional connections PE tube 8 x 11 for max 4 kg h Cl2 SO2 PE tube 10 x 14 for max 10 kg h Cl2 SO2 PVC pipe DN 10 for max 10 kg h Cl2 SO2 PE tube 1 2 od 3 8 NPT threaded up to 200 PPD USA PE tu...

Page 7: ...e and connection chart of a chlorine gas dosing system with vacuum change over device 189 010 1 Gasdetect 2 Adsoroption filter 3 Vacuum regulator with liquid trap 4 Vacuum change over device 5 Chlorin...

Page 8: ...lorine gas have to be checked for leaks 5 1 Leak Test of the Vacuum Side 1 Close the connecting valves of the drums or cylinders 2 Start the injector Thereupon the vacuum lines are evacuated and in th...

Page 9: ...ure the vacu um between change over device and regulator with a vacuum meter The rotameter indicates a flow althoughthesupplybat tery cylinder drum isempty or closed Measure the vacuum after the outle...

Page 10: ...2 4 5 32 6 5 1 4 95 25 33 4 white b r o w n gas inlet II g r e e n 15 189 200 gas inlet I gas outlet type plate connection USA 1 2 sealed with Teflon strip connection PVC pipe DN15 connection PVC pipe...

Page 11: ...U 189 010 en g r e e n white b r o w n 12 4188 310 length 3 m Signal transmitter for remote indication switch direct voltage max 1 0 A contact load max 50 W switch direct voltage 75V switch alternati...

Page 12: ...12 V3 0 U 189 010 en...