Sungazers are installed in a similar fashion as ven6lators. 

A “dry” shee6ng pan is required on both sides of the unit. 

(If the shee6ng profile together with which the Sungazer  will be used is specified in advance, the 

base frame will be made to incorporate  the required “cover flash” ) 

Stop-end roof sheets and install serrated closure at down slope end of the Sungazer 

Back flashings are required  

2.

The unit is despatched in two parts 

Base frame 

Dome, lens and reflectors 

3.

The base frame should be handled by liMing at the corners and not  handled in the centres as the 

“cover flash” might buckle 

4.

All components are installed from above the roof 

Mark the posi6on where the Sungazer is to be installed with a template and cut the hole with a 

cold saw. Sungazer to be posi6oned  central between purlins with sufficient clearance for 

underslung frame 

Posi6on the base frame and  fix to the shee6ng 

Lower the underslung frame through the opening and turn it to line up with the direc6on of the 

base frame and liM to clamp insula6on between underslung frame and base frame. 

Secure the underslung frame to the base frame with the supplied steel strip 6es 

Ensure that the reflectors are secured to the inside ver6cals of the base frame 

Lower the dome over the base frame un6l it reaches the boUom of the frame ensuring that the 

rubber strips have been pushed down 

Secure the dome to the frame at the 6 fixing points with s6tching screws 

5.

Install back flashings 

 

Summary of Contents for Sungazer

Page 1: ...Sungazer Installa on Procedure...

Page 2: ...ed from above the roof Mark the posi6on where the Sungazer is to be installed with a template and cut the hole with a cold saw Sungazer to be posi6oned central between purlins with su cient clearance...

Page 3: ...er 1270 over Sungazer frame Sungazer frame support beam por6on Klip Lok 700 shee6ng Sliding brackets to be used on side sheets when length exceeds 30m for steel sheets 20m for aluminium sheets For sho...

Page 4: ......

Page 5: ...Mark the posi on where the Sungazer is to be installed with a template...

Page 6: ...Remove insula on...

Page 7: ...Place base frame in posi on and secure note single upstand nearest to Apex...

Page 8: ...ough opening and align with base frame ensuring that insula on material is clamped between underslung and base frame Tie underslung frame to base frame with es provided Tie Strap feed both legs throug...

Page 9: ...Tie Strap closest to frame through and bend over this is the leg that keeps underslung frame 6ght against ceiling Step 3 Same for second Tie Strap per re ector side Step 4 Slide cheek plate re ector s...

Page 10: ...Place lens in posi on on top of underslung frame...

Page 11: ...oints Secure dome carefully against 2nd brackets with tech screws rubber washers hole in perspex dome to be pre drilled slightly larger than shaM of fastener Corner view note rubber seal is pushed dow...

Page 12: ...Install back ashings...

Page 13: ......

Page 14: ...Op on for improved performance Follow slides below...

Page 15: ...formance 1 Nip addi6onal re ector strip of same size as installed re ector strip at approximately at third posi6on from ends for a depth of 20mm 2 Slide the addi6onal re ector strip into installed re...

Page 16: ...Slide addi6onal re ector strip into exis6ng re ector strip and allow to protrude above the rest...

Page 17: ...ower the dome by star ng on the south side and allowing the addi onal re ector strip to be gently pushed over on the inside of dome while being lowered onto the base frame and secure to 6 x xing point...

Page 18: ......

Reviews: