LAY OUT THE BUILDING SITE

After the site is prepared, lay out the building site.

Taking these steps 

before

 assembling the shelter saves 

time and ensures that the structure is positioned as 

desired. 

Ground posts must be driven to the proper depth. Width of 

the shelter is measured from the center of one ground post 

to the center of the remaining ground post.

SQUARE THE SITE

Gather the parts:
•  Ground posts
•  Post driver
1.  Identify a corner where a ground post will be positioned 

and drive the first ground post into the ground.  

 

NOTE: 

Insert the ground post driver into the top of 

the ground post to protect the post and drive the post 

into the ground. 

The top of the post will be one (1) foot 

above the finished grade when properly driven.

 

 

4.  String a line at least as long as the building from the 

first stake at 90°. 

 

NOTE:

 A transit can be used to ensure an accurate 90°  

angle, or the 3-4-5 rule can be used. Refer to diagram.  

Using multiples of 3-4-5 such as 6-8-10 or 12-16-20  

helps to maintain an accurate 90° angle.

5.  After squaring the position of the building, measure the 

length and drive the next corner ground post.

6.  Repeat the same step for the last corner post. 

 

NOTE:

 The distance measured diagonally between 

corner posts must be equal for the building to be 

square.

7.  Check all dimensions (and adjust if needed) before 

driving the remaining posts to the required height.

8.  After all corner posts are accurately installed, tie a 

string line between the tops of the corner ground posts 

on the same side of the shelter. The string is used to 

identify the tops of all remaining ground posts. The 

string must remain tight and level.

9.  Use a tape measure to mark the 48" on-center 

locations of the remaining ground posts.

10. Drive the remaining ground posts into the ground at the 

required 48" on-center width and the height identified 

by the string. 

 

NOTE:

 Verify that the holes in the ground posts are in 

the proper position and that each post is plumb and 

driven to the correct depth. 

 

After the rafters have been assembled, the rafter ends 

are secured to the ground post using the upper hole.  

 

The bottom two (2) holes on the ground post are used 

for the optional baseboards.

11.  Continue with the 

Rafter Assembly

 steps that follow.

ATTENTION:

 Position the pre-drilled holes facing to the 

inside/outside of the shelter so they can be aligned with 

the bolt holes in the rafter legs. 

 

To align the bolt holes in the ground posts with those 

in the rafter 

after driving the ground posts,

 insert a 

tapered rod or pry bar into a ground post bolt hole and 

turn the post using the rod or pry bar.

2.  After the first corner ground post is in place, string a 

line the width of the building (center-to-center) and 

drive the second ground post into the ground just 

enough to hold it in place.

3.  Use a transit or line level to drive the second corner 

post to the same depth as the first ground post.

Outside of 

Shelter

Inside of 

Shelter

Ground 

Post

Summary of Contents for Round Premium PB01660R4

Page 1: ...hoto may show a different but similar model 2020 GrowSpan All Rights Reserved Reproduction is prohibited without permission STK DIMENSIONS PB01660R4 14 W x 10 H x 24 L PB01662R4 14 W x 10 H x 36 L PB0...

Page 2: ...manufacturer s warranty and may cause serious injury and damage LOCATION Choosing the proper location is an important step before you begin to assemble the structure The following suggestions and pre...

Page 3: ...in cover if equipped This applies to fabric covers that stretch over the frame assembly Your shelter may include roof panels or side panels or both 11 Read the Care and Maintenance information at the...

Page 4: ...ed for buildings with roll up sides Materials for baseboards and ribbon boards are not included and are supplied by customer ATTENTION Fasteners to secure boards to building frame are included Recomme...

Page 5: ...nd Plain Rafter Sections 102569 Bearing 102717 Gearbox Drive 102198 U Channel Spring 102197 Poly Latch U Channel 102570 Aluminum Channel Zippered End Panel QH1400 Band Clamp FRAME ASSEMBLY NOTE During...

Page 6: ...Premium High Tunnel For details please see section Assembling the Round Premium High Tunnel Components See illustration below to identify main parts of high tunnel 1 Locate the required parts for each...

Page 7: ...he remaining posts to the required height 8 After all corner posts are accurately installed tie a string line between the tops of the corner ground posts on the same side of the shelter The string is...

Page 8: ...in ground post Install the screws so they will not touch the cover once it is installed This is typically on the backside of the rafter which will be the surface visible from the inside of the high tu...

Page 9: ...r length and one 1 1 315 x 73 5 131P0735 plain pipe 8 Continue adding rafters and purlin pipe until the frame is assembled Secure all purlin splices using Tek screws See Step 10 9 Finish the purlin ru...

Page 10: ...Angle Bracket Tek Screws View from inside of the shelter Customer Supplied Wood Screws BASEBOARD INSTALLATION RECOMMENDED Gather the parts Treated or recycled plastic lumber supplied by customer Reco...

Page 11: ...y cause serious injury and damage STRUT ASSEMBLY PROCEDURE After the frame is assembled attach a diagonal strut to the brace band and to the baseboard Gather the parts Struts 5 QH1304 5 16 x 1 1 2 lag...

Page 12: ...al from inside the frame after attaching the panels to the end rafters MAIN COVER INSTALLATION After the end panels are installed install the main cover The steps to install the main cover include 1 A...

Page 13: ...me sizes WARNING To prevent damage to the cover and to prevent serious personal injury DO NOT attempt to install the main cover on windy or stormy days 1 Unpack the main cover and position it at the b...

Page 14: ...first end rafter until the entire length of the end of the main cover is secured in place 7 Stretch the cover to the other end of the building and repeat the steps to secure the main cover in the U Ch...

Page 15: ...of the Wrist assembly and attach it to the frame and the roll up side 4 Install the Anti Billow Rope system 5 Test the operation of the roll up side 4 Place the assembled conduit at the base of the si...

Page 16: ...Verify that the lower end of the channel is slightly off the ground to allow it to move freely when the panel is rolled up and down 5 Secure the upper end of the channel by drilling a 3 8 hole through...

Page 17: ...m channel from the ground end This is the free end of the channel 13 Roll the cover conduit up to the Twist of the Wrist assembly 14 Attach the conduit to the square shaft of the assembly by inserting...

Page 18: ...nance information that follows NOTE If the poly latch U Channel was attached to a ribbon board as suggested the eyebolt can be mounted through the poly latch channel and ribbon board to the inside of...

Page 19: ...anytime Remove debris and objects that may accumulate on the cover Use tools that will not damage the cover when removing debris Remove snow to prevent excess accumulation Use tools that will not dama...

Page 20: ...ELS 20 Revision date 01 01 20 QUICK START GUIDE 14 Wide Round Premium High Tunnels Frame shown may differ in length from actual frame Height 14 0 9 10 11 16 Width 1 10 11 16 Sidewall Height Grid Repre...

Page 21: ...GROWSPAN ROUND PREMIUM HIGH TUNNELS 21 Revision date 01 01 20 FRONT PROFILE 14R1301 14R1301 14R1303 14R1302 102676 102676 End 102855 Middle 102479 131S027D 131S027D...

Page 22: ...AN ROUND PREMIUM HIGH TUNNELS 22 Revision date 01 01 20 SIDE PROFILE PB01660R4 24 0 Length 3 131S075 1 131P0735 Purlin Cover Conduit Customer Supplied Baseboard 4 0 on center Rafter Spacing center to...

Page 23: ...AN ROUND PREMIUM HIGH TUNNELS 23 Revision date 01 01 20 SIDE PROFILE PB01662R4 36 0 Length 5 131S075 1 131P0735 Purlin Cover Conduit Customer Supplied Baseboard 4 0 on center Rafter Spacing center to...

Page 24: ...AN ROUND PREMIUM HIGH TUNNELS 24 Revision date 01 01 20 SIDE PROFILE PB01664R4 7 131S075 1 131P0735 Purlin Cover Conduit 4 0 on center Rafter Spacing 48 0 Length center to center Customer Supplied Bas...

Page 25: ...ter Purlin Connection 102479 Purlin Rafter View 2 Mid Rafter Purlin Connection QH1400 QH1304 Rafter View 3 Rafter Strut Connection View is seen from inside of the shelter End Rafter Purlin Connection...

Reviews: