![GrowSpan 113577 Manual Download Page 6](http://html1.mh-extra.com/html/growspan/113577/113577_manual_2270674006.webp)
66
Revision date: 12.17.14
Complete these steps:
1. If main cover film is installed, remove the spring wire that secures
the cover in the u-channel until the lower edge of the cover is
loose. Also, remove the cover from the end rafter u-channel to
allow for the installation of the 111613Z144.
NOTE:
Dashed line identifies the u-channel that must be
removed to allow for the installation of the rainwater catch drain
components. For a new construction, first install the ribbon board
as instructed in the building instruction manual and then install
the 111613Z144 as noted in these diagrams.
1
RAINWATER CATCH DRAIN INSTALLATION
Assembly Instructions
Diagram shows
the 111613Z144
installed.
111613Z144
Not to
exceed
16".
Not to
exceed
16".
Building Cover
*Included with rainwater
catch drain kit.
**Supplied by customer.
*111613Z144
Secure to rafter using
*FA4482B Tek screws.
**Ribbon board and
u-channel for drop-down
or roll-up side panel. See
main building instructions
to install.
Single u-channel is
shown. Depending on
building design, double
u-channel may also be in
this position to secure roof
material and roll-up side.
U-channel attached
to end rafters. Cut
to allow for the
installation of the kit
components.
2. Using the diagram,
determine where
to install the
111613Z144 that
runs the length of
the building frame
along the side.
3. Mark height at both
ends ensuring that
the 111613Z144 will
be level along the
side. Use a string
line or chalk line to
mark each rafter.
4. Attach the
111613Z144 to
building rafters
using FA4482B Tek
screws included
with the kit. Install
one screw every
48" on-center to
secure.
ATTENTION:
Building design must include a roll-up or drop-down side. If your
building does not include either of these, contact customer service to purchase
additional u-channel and spring wire.
Do not continue with the installation of this
kit without consulting with customer service.