T27978 50-Ton Hydraulic Press (Mfd. 12/16)
-3-
3. Attach hydraulic reservoir assembly to out-
side of press frame (see
Figure 5) by thread-
ing (4) M10-1.5 x 30 hex bolts, 10mm flat
washers, and 10mm lock washers through
frame mounting bracket into threaded holes
of hydraulic assembly.
4. Attach winch to outside of press frame, as
shown in
Figure 6, using (2) M10-1.5 x 25
hex bolts, 10mm flat washers, and M10-1.5
hex nuts.
Anchoring to Floor
Anchoring machinery to the floor prevents tipping
or shifting and reduces vibration that may occur
during operation, resulting in a machine that runs
slightly quieter and feels more solid.
If the machine will be installed in a commercial or
workplace setting, local codes may require that it
be anchored to the floor.
If not required by any local codes, fastening the
machine to the floor is an optional step. If you
choose not to do this with your machine, we rec-
ommend placing it on machine mounts, as these
provide an easy method for leveling and they have
vibration-absorbing pads.
Lag shield anchors with lag screws (see below)
are a popular way to anchor machinery to a con-
crete floor, because the anchors sit flush with the
floor surface, making it easy to unbolt and move
the machine later, if needed. However, anytime
local codes apply, you MUST follow the anchoring
methodology specified by the code.
Machine Base
Concrete
Lag Screw
Lag Shield Anchor
Flat Washer
Drilled Hole
Figure 7. Popular method for anchoring
machinery to a concrete floor.
Anchoring to Concrete Floors
Number of Mounting Holes ............................ 4
Diameter of Mounting Hardware .................
3
⁄
8
"
Figure 5. Mounting hydraulic assembly.
Hydraulic
Assembly
x 4
Frame
Mounting
Bracket
Figure 6. Mounting winch to press frame.
Winch
x 2