Model G0857/G0858 (Mfd. Since 07/19)
-23-
Tightening Belt
The final step in the setup process must be done
after approximately 16 hours of operation. During
this first 16 hours, the belt will stretch and seat
into the pulley groove. After this time, you must
re-tension the belt to avoid slippage and burn out.
Refer to
Page 51 when you are ready to perform
this important adjustment.
Note: Pulleys and belt can get hot. This is a nor-
mal condition. Allow them to cool before making
adjustments.
A small amount of black belt dust at the bottom
of the belt housing is normal during the life of the
machine and does not indicate a problem with the
machine or belt.
Test Run
Once assembly is complete, test run the machine
to ensure it is properly connected to power and
safety components are functioning correctly.
If you find an unusual problem during the test run,
immediately stop the machine, disconnect it from
power, and fix the problem BEFORE operating the
machine again. The
Troubleshooting table in the
SERVICE section of this manual can help.
DO NOT start machine until all preceding
setup instructions have been performed.
Operating an improperly set up machine
may result in malfunction or unexpect-
ed results that can lead to serious injury,
death, or machine/property damage.
Serious injury or death can result from
using this machine BEFORE understanding
its controls and related safety information.
DO NOT operate, or allow others to operate,
machine until the information is understood.
To test run machine:
1. Clear all setup tools away from machine.
2. Connect machine to power supply.
3. Push ON button to start machine. A correctly
operating machine runs smoothly with little or
no vibration or rubbing noises.
4. Push STOP paddle to stop machine.
Congratulations! The Test Run is complete.
Summary of Contents for G0857
Page 65: ......