GreenAire RAH-SAU series Installation And Operation Manual Download Page 3

E.

Pipe the drain line

Again be sure not to trap water. If necessary employ a condensate pump/drain to
elevate the drain water and evacuate it during drain cycles.

II) RO System Location and Piping:

A. Now install the Reverse

mountable with simply two screws and can be hung as self supporting. Follow
the instructions outlined below
respective connections. All connections are simple quick connec
recommended that a shut off valve be placed in line after tapping the domestic
water line for the RO System supply.

1) Locate and connect the

equipment. This will be the right side as you face the system. The
supply side will consist of Black ¼” tubing.

2) Locate the Yellow drain line, and place in an appropriate area for

drainage.

HUMIDIFICATION SEASON IS MONTHS AWAY.
CONDENSATE PUMP

3) Locate the b

humidifiers
system metal frame)
storage tank.
proximity to the RO System.

4)

Make sure to open the valve at the top of the storage tank.

5) Once installed, allow the system to run for approximately 15

minutes to flush completely. Make sure there are no leaks, parts
can come loose in shippin

6) The RO System will run until all the humidifier supply lines and

storage tank are filled and charged to the pressure of the building.
This may take several hours to happen.

7) PLEASE N

WATER SUPPLY TO THE RO SYSTEM.

if this is a problem)

B. Pipe supply piping from

Panel/Generator or STS Box

C. Open the inline water valve off of the build

the filling of water to the
filling the clear water filter housings on the RO System.

D. Check for leaks. As stated above The RO System will run until all the humidifier

supply lines and storage tank are filled and charged to the pressure of the
building. This may take several hours to happen. Again, make sure that the
drain is working – if the drain line is fed to a condensate pump the pump MUST
BE OPERABLE! The RO System h

Pipe the drain line from the Control Panel to an appropriate drain location.

Again be sure not to trap water. If necessary employ a condensate pump/drain to
elevate the drain water and evacuate it during drain cycles.

II) RO System Location and Piping:

everse Osmosis (RO) Water system. These systems are wall

mountable with simply two screws and can be hung as self supporting. Follow

outlined below for connecting the colored tubes to their

respective connections. All connections are simple quick connec
recommended that a shut off valve be placed in line after tapping the domestic
water line for the RO System supply.

Locate and connect the domestic water supply side of the

quipment. This will be the right side as you face the system. The

ply side will consist of Black ¼” tubing.

Locate the Yellow drain line, and place in an appropriate area for
drainage.

NOTE: DRAIN MUST BE OPERABLE! EVEN IF THE

HUMIDIFICATION SEASON IS MONTHS AWAY.
CONDENSATE PUMP – IT MUST BE ON LINE!

Locate the blue product water line that will provide
humidifiers. Utilize a “t” connector (provided and taped to the RO
system metal frame) to hook up the product water (blue line) to the
storage tank. Locate the 2.5 gallon storage/bladder
proximity to the RO System.

Make sure to open the valve at the top of the storage tank.

Once installed, allow the system to run for approximately 15
minutes to flush completely. Make sure there are no leaks, parts
can come loose in shipping. Hand tightening may be necessary.
The RO System will run until all the humidifier supply lines and
storage tank are filled and charged to the pressure of the building.
This may take several hours to happen.

PLEASE NOTE: 35 PSI MINIMUM REQUIRED ON INCO
WATER SUPPLY TO THE RO SYSTEM.

(Consult with the Factory

if this is a problem)

Pipe supply piping from the RO System to the fitting on the side of the

or STS Box labeled “

water in

”.

Open the inline water valve off of the building domestic water supply to begin

filling of water to the RO System. You should notice water immediately

filling the clear water filter housings on the RO System.

As stated above The RO System will run until all the humidifier

lines and storage tank are filled and charged to the pressure of the

building. This may take several hours to happen. Again, make sure that the

if the drain line is fed to a condensate pump the pump MUST

The RO System has an automatic shut off valve (ASO) that

3

to an appropriate drain location.

Again be sure not to trap water. If necessary employ a condensate pump/drain to

Water system. These systems are wall

mountable with simply two screws and can be hung as self supporting. Follow

for connecting the colored tubes to their

respective connections. All connections are simple quick connects. It is
recommended that a shut off valve be placed in line after tapping the domestic

supply side of the

quipment. This will be the right side as you face the system. The

Locate the Yellow drain line, and place in an appropriate area for

NOTE: DRAIN MUST BE OPERABLE! EVEN IF THE

IF PIPED TO A

e product water line that will provide RO water to the

(provided and taped to the RO

to hook up the product water (blue line) to the

Locate the 2.5 gallon storage/bladder tank in close

Make sure to open the valve at the top of the storage tank.

Once installed, allow the system to run for approximately 15
minutes to flush completely. Make sure there are no leaks, parts

g. Hand tightening may be necessary.

The RO System will run until all the humidifier supply lines and
storage tank are filled and charged to the pressure of the building.

OTE: 35 PSI MINIMUM REQUIRED ON INCOMING

(Consult with the Factory

the RO System to the fitting on the side of the Control

ing domestic water supply to begin

System. You should notice water immediately

As stated above The RO System will run until all the humidifier

lines and storage tank are filled and charged to the pressure of the

building. This may take several hours to happen. Again, make sure that the

if the drain line is fed to a condensate pump the pump MUST

as an automatic shut off valve (ASO) that

Summary of Contents for RAH-SAU series

Page 1: ...INSTALLATION AND OPERATION FOR VS 7 14 INSTALLATION AND OPERATION FOR RAH SAU Series 1 INSTALLATION AND OPERATION...

Page 2: ...eference of the End User or Installer The following rules should be followed Place the Control Panel in a place where the outlet fog will not impinge on any surfaces Make sure to verify the air patter...

Page 3: ...vide humidifiers Utilize a t connector provided and taped to the RO system metal frame to hook up the product water blue line to the storage tank Locate the 2 5 gallon storage bladder proximity to the...

Page 4: ...Generator panel at the appropriately labeled locations on the terminals Refer to the Wiring Diagram provided with your unit for proper landing locations and line sizes Shielded control wire is recomme...

Page 5: ...ed to a drain Turning the System On go to the control panel and make sure the panel on off switch is off open up the control panel and make sure the circuit breaker CB is off if CB is showing green th...

Page 6: ...ith the system it should become active and show figures on it s display The should correspond to both the actual humidity level and the target set point humidity level Make sure their respective readi...

Page 7: ...turned off and verify that the Humidifier turns off as well as air flow stops b With the AC System back on if possible locate the HiLimit switch and lower its setting to as low as it can go The switc...

Page 8: ...xcessive continuous run time when humidifier is undersized or the space really needs more humidifiers but the customer elected not to furnish and install them If your model has a timer delay relay go...

Page 9: ...ure that the comes on Verify that the air flow switch has closed after properly sensing that air is moving in the duct Verify that the HiLimit switch circuit is closed Check the Wet Switch and verify...

Page 10: ...on when there is a call for humidification and not just when there is a call for heat There is a dry contact relay in the panel for exactly this purpose Contact the Installer to verify that he utilize...

Page 11: ...g sure all the UPC discs that should be running are indeed doing so You may do this by observing the operation with a flash light and peering through the plastic lid or taking the lid off see above in...

Page 12: ...12...

Page 13: ...13...

Page 14: ...14...

Page 15: ...15...

Page 16: ...16...

Page 17: ...17...

Page 18: ...18...

Page 19: ...19...

Page 20: ...120V 1PH Power On R 96 VA 7 6 UPC TANK 3 2 WET SWITCH 9 40 VA 10 WIRING FOR RAH SAU LAB UNIT WITH VECTOR CONTROLLER G Fog On Fill SV 2 11 A 17B Low Water CR3 NC WET SWITCH R WS 12B CR3 CR4 FLOAT SWITC...

Page 21: ...Idec Single Pole Relay 6048 Idec Single Pole Socket 6050 EMI RFI Fan Guard PARTS LIST Item Description 2 4 MHz Nebulizer Board Model 579R3 304SS with welds stand brackets top flange w PEMS and bottom...

Page 22: ...y or Factory Representative for current pricing Fan Guard for 4 69 Fan Bulkhead Conn 1 4T x 1 8MPT Brass Part B 400 11 2 clear w paper back in square ft units 10 Amp fuse 12 32 dia time delay 250 VAC...

Reviews: