APPENDIX A - CONTROL MODULE

Table 8  -  Troubleshooting Error Codes

Error 

Code 

Number

De

fi

 nition

Consequence

2

Pressure switch failed to open (stuck closed).

Wait for recovery

4

Flame current too low. Check for 

fl

 ame.

Non critical alarm

6

Flame sensed out of normal sequence (before opening or after closing gas valve).

Soft lockout

18

Gas valve relays welded. Five consecutive soft lockouts.

Hard lockout

23

Flame sensed during prepurge ( before gas valve signaled opened).

Soft lockout

24

Flame sensed during postpurge (after gas valve signaled closed).

Soft lockout

29

Pressure switch failed to close (Contacts stuck open)

Wait for recovery

32

Sensor 1 error.  Temperature sensor in well is not reading correctly.                       

Verify it is connected to board.  Replace if necessary.

Wait for recovery

57

Igniter 

fl

 ame rod shorted to burner ground

Wait for recovery

58

Igniter 

fl

 ame rod shorted to burner ground.  Repair or replace igniter.

Wait for recovery

59

Line Voltage error - voltage out of speci

fi

 cation high or low (15-37V (44-66Hz))

Wait for recovery

60

Applies only to thermostats having on-board transformer.  
Polarity is wrong in this case.

Wait for recovery

Thermostat input higher than threshold.

61

Line voltage unstable - possibly too may heavy loads switching on and off causing 

erratic supply voltage.

Wait for recovery

62

Soft lockout: maximum number of retries exceeded.

Soft lockout

Soft lockout is reset after one hour if alarm reason disappears.

63

Soft lockout: maximum number of recycles exceeded.

Soft lockout

64

Soft Lockout - electronics failure. On-board self diagnostics detected error.

Soft lockout

65

Over temperature error.  Sensor measured temperature in excess of maximum 

allowable limit.

Soft lockout

 Note: Soft lockout time is 1 hour or manual reset. Hard lockout requires manual reset.

A.9 Intermittent Pilot

Ignition System Checks

STEP 1: 

Check ignition cable.

• Verify ignition cable does not run in contact with metal 

surfaces.

• Verify only factory supplied Ignition cable (or approved 

replacement) is used.

• Verify connections to ignition module and igniter or 

igniter-sensor are clean and tight.

• Verify ignition cable provides good electrical continuity.

STEP 2:

Verify ignition system grounding. Nuisance shutdowns are 

often caused poor or erratic grounding.
Common ground is required for module and pilot  burner/

igniter sensor.

— Check for good metal-to-metal contact between
  pilot burner bracket and the main burner.
— Check ground lead from GND (BURNER) terminal 

on module to pilot burner.  Verify connections are 

clean and tight. If wire is damaged or deteriorated, 

replace with No. 14-18 gauge, moisture-resistant, 

thermoplastic insulated wire with 105°C [221°F] 

minimum rating.

— Check ceramic 

fl

 ame rod insulator for cracks or 

evidence of exposure to extreme heat, which can 

permit leakage to ground. Replace pilot burner/igniter 

sensor and provide shield if necessary.

— If 

fl

 ame rod or bracket is bent out of position, restore 

to correct position.

Summary of Contents for GMPVB

Page 1: ...VB Gas Fired Hot Water Induced Draft Boiler INSTALLATION OPERATION MAINTENANCE MANUAL Series II Models GMPVB 42 GMPVB 150 GMPVB 75 GMPVB 188 GMPVB 112 GMPVB 225 Manufactured by ECR International Inc 2...

Page 2: ...is boiler must be performed by a qualified installer TO THE INSTALLER Leave all instructions with boiler for future reference When this product is installed in the Commonwealth of Massachusetts the in...

Page 3: ...d be based upon Net AHRI Rating being equal to or greater than calculated heat loss of building Manufacturer should be consulted before selecting a boiler for installations having unusual piping and p...

Page 4: ...4 DIMENSIONS Model Width A GMPVB 42 11 GMPVB 75 14 1 4 GMPVB 112 17 1 2 GMPVB 150 20 3 4 GMPVB 187 24 GMPVB 225 27 1 4...

Page 5: ...ting installation See rating and capacity table 8 When installed in utility room door should be wide enough to allow largest boiler part to enter or to permit replacement of another appliance such as...

Page 6: ...s communicating directly or by ducts with outdoors Two Permanent Opening Method Provide opening commencing within 12 inches of top and second opening commencing within 12 inches of bottom enclosure Di...

Page 7: ...all be installed to relief valve outlet connection to avoid burns scalding or water damage due to discharge of steam and or hot water during operation Discharge line shall connect to relief valve outl...

Page 8: ...8 INSTALLATION SYSTEM PIPING Figure 3 Forced Hot Water Typical Piping Figure 4 Forced Hot Water Typical Piping With Zone Control Valve...

Page 9: ...exposed to refrigerated air circulation piping system shall be equipped with flow control valves or other automatic means to prevent gravity circulation of boiler water during cooling cycle INSTALLATI...

Page 10: ...as directly as possible with as few elbows as possible 7 Where possible it is recommended to common vent water heater and boiler Consult appropriate Vent Sizing Tables in National Fuel Gas Code for sp...

Page 11: ...n to gas vents or chimneys vent installations shall be in accordance with Venting of Equipment of the National Fuel Gas Code ANSI Z223 1 NFPA 54 or applicable provisions of the local building codes Fi...

Page 12: ...ng system Turn on any exhaust fans such as range hoods and bathroom exhausts so they will operate at maximum speed Do not operate a summer exhaust fan Close fireplace dampers 4 Place in operation the...

Page 13: ...eter 90 elbow or 3 feet of straight pipe for 3 diameter 90 elbow 2 3 4 5 Section Boilers use 3 vent pipe for 6 7 Section Boilers use 4 vent pipe CHOICE OF VENT PIPE MATERIAL U L Listed Z Flex Z Vent S...

Page 14: ...0 elbow pointing down fitted with a minimum 1 4 mesh screen to keep out rodents and birds The elbow shall be of the same material and size as vent pipe The elbow exit should be at least 6 away from ex...

Page 15: ...egulators and relief equipment See Figure 9 United States Terminate vent system at least 4 feet 1 22m horizontally from and in no case above or below unless a 4 feet 1 22m horizontal distance is maint...

Page 16: ...fore operating appliance B For Heat Fab Saf T Vent stainless steel vent pipe use a high temperature silicone sealant rated for 550 F The outside of the male end and inside of the female end of the pip...

Page 17: ...boiler to prevent collection of condensate throughout the assembly 7 Allow the sealant to cure for 24 hours before operating the appliance D For ProTech Systems FasNSeal stainless steel vent pipe no...

Page 18: ...ls Power Venter 2 3 4 5 SWG 4D 6 7 SWG 5D Some possible reasons for using a power venter for sidewall venting 1 May be preferred by local codes 2 Need a vent piping run beyond 30 9 1m but not more tha...

Page 19: ...g Install manual shut off valve in vertical pipe about 5 feet 1 5m above floor See Figure 10 Tighten all joints securely Propane gas connections should only be made by licensed propane installer Two s...

Page 20: ...pacity BTU Per Hour Input Includes Fittings 1 1 20 92 000 190 000 350 000 625 000 40 63 000 130 000 245 000 445 000 60 50 000 105 000 195 000 365 000 Table 6 PROPANE GAS Length of Pipe Ft Pipe Capacit...

Page 21: ...ot install a thermostat where it will be affected by drafts hot or cold pipes sunlight lighting fixtures televisions a fireplace or a chimney 4 Check thermostat operation by raising and lowering therm...

Page 22: ...er water temperature reaches high limit set point high limit contacts open cutting power to blower and pilot control Burners extinguish and blower stops Circulator pump continues to run as long as the...

Page 23: ...23 WIRING DIAGRAMS Figure 12 Control Module Damper is not an option...

Page 24: ...s Repeat until you have covered every radiation unit in system End at highest unit in system If units have automatic vents manual venting is unnecessary but it will speed up proper filling of system I...

Page 25: ...ob WARNING If you do not follow these instructions exactly a fire or explosion may result causing property damage personal injury or loss of life This appliance is equipped with an ignition device whi...

Page 26: ...quire primary air adjustment and are not equipped with primary air shutters Main burner flames form sharp blue inner cones in softer blue outer mantel with no yellow Puffs of air from blow ing on flam...

Page 27: ...supply to burners 3 Turn your thermostat up to call for heat and let your boiler run until temperature of water reaches limit setting Gas valve shuts off and circulator keeps running until thermostat...

Page 28: ...ater left in to freeze will crack pipes and or boiler Cleaning Your Boiler And Burners Flue passages between sections should be examined yearly and cleaned if necessary To clean Remove burners pilot a...

Page 29: ...trical contact Check all control terminals and wire joints Chimney flue is blocked Pressure switch will not close and pilot spark will not operate to start pilot Have your service technician check and...

Page 30: ...o expand as temperature changes Diaphragm type tank can be mounted on air purger fitting or at any convenient place in supply or return line AIR ELIMINATING FITTING AIR PURGER Air purger is used to re...

Page 31: ...ed Factory Pressure Switch Set point 0 4 wc for 2 5 section boilers 0 5 w c for 6 7 section boilers Rollout Switch FLAME ROLLOUT SAFETY SHUTOFF Rollout switch is temperature sensitive fuse link device...

Page 32: ...TT using wire nuts Ensure remaining Molex plug connectors have not worked loose during transit Check sensing bulb is fully inserted in well and is not loose A 3 Adjusting Settings To discourage unauth...

Page 33: ...ion was not detected and delay is called before retry Recycle delay Flame signal was lost and delay is called before retry 11 Wait for pressure switch to open failed to close Inducer is still off Pres...

Page 34: ...out models must be reset through key buttons and display On retry models wait for retry or reset at thermostat Check for correct installation and wiring before replacing any component Control module c...

Page 35: ...ut Soft lockout is reset after one hour if alarm reason disappears 63 Soft lockout maximum number of recycles exceeded Soft lockout 64 Soft Lockout electronics failure On board self diagnostics detect...

Page 36: ...ged wire Check for cracked ceramic insulator which can cause short to ground and replace igniter sensor if necessary At gas valve disconnect main valve wire from MV terminal Turn on power and set ther...

Page 37: ...Date Service Performed Company Name Tech Initials Company Address Phone...

Page 38: ...NOTES...

Page 39: ...Date Service Performed Company Name Tech Initials Company Address Phone...

Page 40: ...Manufactured by ECR International Inc 2201 Dwyer Avenue Utica NY 13504 4729 web site www ecrinternational com...

Reviews: