Installation
24
334135B
Install Pump Tubes
See
on page 65 for kit
numbers.
NOTE:
Ensure that high volume and low volume pump
tubes are installed on the correct side of the machine.
5.
Secure the piston support ring, piston, and washer
to the piston shaft using the piston screw. Tighten
the piston screw until the screw stops rotating, then
turn the screw an additional 1/8 turn.
6.
Lubricate the tube pump o-rings. Install the tube
pump and o-rings as shown.
7.
Install the pump cap onto the assembly using the
four bolts. Finger tighten the bolts, then torque the
bolts to 350 in-lb (40 N•m) in a crisscross pattern.
Install the Chemical Hoses.
Install the chemical hoses and tighten to prevent leaks.
NOTE:
Ensure that high volume and low volume hoses
are installed on the correct side of the machine.
Install the Hydracheck Kit.
Perform
HydraCheck Kit Installation, 24W336
starting
on page 40.
Install the Tanks.
Refer to the PR70 and PR70v Feed Systems, Instruc-
tions-Parts manual for details.
Install the Dispense Valve and Support Arm, if
needed.
Install the dispense valve as necessary to prevent
movement. Connect the required air lines from the dis-
pense valve to the machine.
High Volume
Low Volume
1
2
3
4
Air to Close (O)
Air to Open (I)
Summary of Contents for PR70e
Page 9: ...Component Identification 334135B 9...
Page 12: ...Recommended Parts 12 334135B Mixers 1301 1303 1302 Assembly LC0061 Shown ti12442a...
Page 19: ...Recommended Parts 334135B 19...
Page 56: ...Schematics 56 334135B Schematics Electrical Schematics FIG 21 Electrical Schematic...
Page 57: ...Schematics 334135B 57 FIG 22 Electrical Schematic...
Page 59: ...Schematics 334135B 59...
Page 67: ...Dimensions 334135B 67 Dimensions 25 1 in 65 cm 27 9 in 71 cm 9 0 in 23 cm 15 5 in 40 cm...
Page 68: ...Dimensions 68 334135B...