RAISED RUNWAY SYSTEM
www.gillathletics.com
INSTRR100
9/12/2013
800-637-3090
All rights reserved.
Page 2 of 5
Copyright
2013 by Gill Athletics.
INSTRUCTION MANUAL
37.62m / 2.46m = 15.29
HOW TO ORDER A POLE VAULT RUNWAY
15.29 rounds up to 16
40m - 2.38m = 37.62m
____ x RR100 - Basic Runway Section
1
____ x RR500 - PV Pit Riser Pad
____ x RR200 - Vault Box Runway Section
5. Add 2 (to support the PV Standards)
16 + 2 = 18 total basic runway sections
Sections needed, use the following formula.
1. Determine the desired runway length in meters
2. Subtract 2.38
3. Divide by 2.46
4. Round up
653.......................10
65411...................10
65611...................12
66311...................12
66511...................14
66711...................16
To determine the number of PV Pit Riser Pads needed,
consult the RR500 spec sheet for more details.
PV Pit Model Recommended Pit Riser Qty
To determine the number of Basic Runway
Example:
The NCAA recommends a minimum runway length of 40 meters.
Minimum Runway Length
NCAA..........40 meters
NFHS..........40 meters
8'-1"
137'-2"
41.80 m
7'-10"
2.38 m
2.46 m