The standard probe (Figure 1-

2) consists of a 1” (2.5 cm) diameter hydrocarbon float and a 1” (2.5 cm) 

diameter water float. When the hydrocarbon float rises, it activates a time delay which turns on the system 
(after a user-set period of time). This time may be varied by adjusting the potentiometer within the EP box. A 
preset delay can prevent the pump from turning on and off too frequently. The water float prevents the pump 
from running when the intake is in water. 
 

 

 
 

Figure 1-2:

 Product Probe Assembly 

 

Summary of Contents for Shallow Well Probe Scavenger

Page 1: ...Rev 7 12 2018 Part 16030005 Shallow Well Probe Scavenger Installation and Operation Manual...

Page 2: ......

Page 3: ...2 System Installation 8 SWPS Control System 8 Place the Intake Assembly and Product Probe in the well 9 Water Table Depression Pump WTDP 9 PCM Controls 9 Tankfull Probe 10 Product Float 10 Water HI fl...

Page 4: ...d not proceed until you read and thoroughly understand the WARNING message A raised hand icon indicates CAUTION information that relates to a situation or condition that could lead to equipment malfun...

Page 5: ...e itself is intrinsically safe The system consists of a Pump Control Module PCM Figure 1 1 a product probe Figure 1 2 a Tankfull probe Figure 1 3 and an intake assembly Figure 1 4 The standard unit ha...

Page 6: ...ises it activates a time delay which turns on the system after a user set period of time This time may be varied by adjusting the potentiometer within the EP box A preset delay can prevent the pump fr...

Page 7: ...blocks Pump Motor The motor 1 4HP 1725 rpm is explosion proof and has thermal overload protection A self priming gear pump is attached to the motor with a three part flexible coupling This motor is us...

Page 8: ...t fits into the collection tank and shuts off the pump when the tank is full It also acts as a safety device in that it needs to be connected for the SWPS to function Consult Geotech for other options...

Page 9: ...layer from the water surface A product float within the probe rises and magnetically activates a switch in the PCM turning on the pump as needed The pump will continue to run until the product float...

Page 10: ...cap within the spare parts bag Connect the output hose to the output adapter running it through the left portal As with the input hose this is easily done by closing first one then the other handle on...

Page 11: ...ate as such that water float rises and turns off the PCM often then it may be necessary to install a WTDP pump with probe to keep the water table level Contact Geotech to discuss alternatives to well...

Page 12: ...ull probe Product Probe Receptacle 3 pin receptacle on top of control box for sensing the following elements of the probe Tankfull Probe The Tankfull probe shown in Figure 1 3 is designed to be mounte...

Page 13: ...O and lift the product probe blue float 8 Holding the probe this way simulates a situation in which the product float has risen and the probe is in product only The pump should start 9 Now lift the fl...

Page 14: ...table and thereby concentrate product in the well Since the water and product pumps are operating independently any change in the level of the water table will require adjustment of the pump intakes...

Page 15: ...the system probes Every week or more often as necessary rinse both probes in clean fuel and or hot water This procedure will prevent fouling of the probes and sticking of the floats Also while the in...

Page 16: ...the box Problem Motor runs on HAND but not on AUTO Solution Most problems on the AUTO setting can be traced to float malfunctions Examine the product float and confirm that it is not heavy and that i...

Page 17: ...2 Check for damaged hoses Replace if necessary Problem Tankfull Probe or Alarm Indicator Light not operational Solution The control panel will not operate if there is a cut in the Tankfull probe cabl...

Page 18: ...when Tankfull float is down A B Open when Tankfull float is up E From pin E to any metal part of the probe there should be continuity Any deviation from this test means the probe is faulty Contact Geo...

Page 19: ...p Power Requirements ____ Voltage ____ Phase ____ Amps ____ Hz Tankfull Cable Hose Lengths Standard _______ft m Power Cord _______ft m Input Hose _______ft m Output Hose Lengths Dimensions Fits in ___...

Page 20: ...18 Figure 6 1 Intake Specifications...

Page 21: ...19 Section 7 System Schematic Figure 7 1 Standard System Assembly...

Page 22: ...115 230V 1PH PPE018004 COUPLING MOTOR 1 2 X1 2 56020002 POWER CORD ASSY 115V 3 4 2011036 25 POWER CORD ASSY 230V 3 4 25FT 2012006 PLUG 115V EP PPE017001 PLUG 230V EP PPE017003 CONTROL RECEPTACLE 3 PI...

Page 23: ...WELL PROBE SCAV 56030008 PROBE BOT HAIRPIN STYLE 00221 HAIRPIN SS 25X 042 00229 COLLAR SHAFT 25 DIA 2010037 PRODUCT FLOAT ASSY SM DIA 2020102 PROBE CSG 1 06IDx12 CTD ORS231004 ASSY WATER FLOAT SM DIA...

Page 24: ...alides e g ethylchloride allyl chloride etc The Aromatic LDFS must be used to recover materials containing aromatic hydrocarbons It has epoxy EFP filter cartridge FEP input hoses modified floats etc M...

Page 25: ...ne p ethyltoluene 1 methyl 4 ethyltoluene Fuel Oil 1 kerosene range oil coal oil Fuel Oil 2 Gasoline hendecane heptane all isomers 2 heptanol 3 heptanol heptylene 1 heptene heptylene 2 trans 2 heptene...

Page 26: ...tergent As a decontamination solution it is readily available is the safest of all the above and is usually strong enough if used generously The use of steam can also be effective for decontamination...

Page 27: ...e Water All solutions and water used for decontamination must be collected If lab analysis indicates that the water and or solutions exceed allowable contamination levels they must be treated as hazar...

Page 28: ...solution usually water to remove contaminants and contaminated wash solutions Long handled soft bristled brushes to help wash and rinse off contaminants Lockers and cabinets for storage of decontamin...

Page 29: ...STORY PROJECT DESCRIPTION DATE 1660 Changed image of user interface on PCM remove 3 channel relay remove relay part numbers Updated parts list Edited for formatting and minor corrections on usage Stel...

Page 30: ...28 NOTES...

Page 31: ...rial Authorization number RMA is required prior to return of any equipment to our facilities please call our 800 number for appropriate location An RMA will be issued upon receipt of your request to r...

Page 32: ...Geotech Environmental Equipment Inc 2650 East 40th Avenue Denver Colorado 80205 303 320 4764 800 833 7958 FAX 303 322 7242 email sales geotechenv com website www geotechenv co...

Reviews: