Unpacking and Inspection
Installation Guidelines for 60 Hz PowerPact™
7
Section 2: Unpacking and Inspection
General
NOTE:
After unpacking, carefully inspect the contents for
damage. It is advised to unpack and inspect the unit
immediately upon delivery to detect any damage which
may have occurred in transit. Any claims for shipping
damage need to be filed as soon as possible with the
freight carrier. This is especially important if the generator
will not be installed for a period of time.
•
This standby generator set is ready for installation
with a factory supplied and pre-mounted base pad
and has a weather protective enclosure intended
for outdoor installation only.
•
This UL listed standby generator set may be
packaged with an automatic transfer switch with
built-in load center. This two-pole switch is rated at
35 A, rated at 250 volts maximum.
•
If any loss or damage is noted at time of delivery,
have the person(s) making the delivery note all
damage on the freight bill or affix their signature
under the consignor’s memo of loss or damage.
•
If a loss or damage is noted after delivery, separate
the damaged materials and contact the carrier for
claim procedures.
•
“Concealed damage” is understood to mean
damage to the contents of a package not evident at
the time of delivery, but discovered later.
Required Tools
•
General SAE and Metric hand tools
– Wrenches
– Sockets
– Screwdrivers
•
Standard electrician’s hand tools
– Drill and bits for mounting and routing conduits
•
4 mm Allen wrench (for access to customer
connections)
•
6 mm Allen wrench (for removing top lid)
•
3/16 in
Allen wrench (test port on fuel regulator)
•
Manometer (for fuel pressure checks)
•
Digital multimeter (DMM) capable of measuring
AC/DC voltage and frequency
•
Torque wrenches
Unpacking
1.
Remove cardboard carton.
2.
If equipped, the optional transfer switch will be
visible on top of the generator.
3.
Remove the wood frame. Lift the transfer switch, if
present, off the generator.
Figure 2-1. Crated Generator
4.
There are four hex socket fasteners securing the
top lid. Remove these fasteners and lift the top lid
from the generator enclosure.
5.
Once the lid is open, remove the front panel by lift-
ing it up and out. Also open the door covering the
customer connection area.
6.
Perform a visual inspection for any hidden freight
damage.