background image

NOTE: Balance must be maintained when moving  circuit
locations from main electrical distribution panel to
emergency load center. Circuit breaker positions
alternate buss bars vertically. Circuits sharing a neutral
wire should either be moved together to adjacent
positions in emergency load center or not moved. If you
are unsure of proper procedure or if your installation
differs from that described in this guide, consult a
licensed professional at this time.

13a. 

Remove the main electrical distribution panel cover.
Remove appropriate size knockout from the bottom
or side of the main panel. (A 2-foot flexible conduit is
pre-wired from the transfer switch with built-in load
center.) Remove threaded lock nut from conduit
coupling.  Feed all wires through knockout into main
panel. Slip lock nut over wires and tighten securely
onto conduit coupling. 

NOTE: Circuits to be moved must be protected by same
size breaker. For example, a 15 amp 120V circuit in
emergency load center will replace a 15 amp 120V
circuit in main panel.

13b.

In your main panel, remove the black (hot) wire from
a circuit breaker that protects a circuit you want to
have powered in the event of a power failure. Wire
nut the black wire to the matching circuit lead wire
from the emergency circuit breaker from load center
in the transfer switch. (All circuit wires are color
coded and labeled for easy identification).  Repeat
this process with remaining circuits to be powered
by the generator. White wires (neutral) in your main
distribution panel should remain connected to
neutral bar. It is not necessary to move them.  The
emergency load center in the transfer switch supplies
the following circuits: (5) 15A/120V, (3) 20A/120V,
(1) 20A/240V and (1) 30A/240V.

14. 

Install the 70 Amp double pole circuit breaker that
you have purchased into main electrical distribution
panel. This circuit breaker 

must be compatible with

your main electrical distribution panel.

It may be

necessary to reposition remaining circuit breakers or
remove circuit breakers that have been disconnected
to accommodate the insertion of the 70 Amp double
pole circuit breaker.  Connect white wire to the main
distribution panel neutral bar. Connect solid green
wire to main electrical panel ground bar.  Connect the
black and red wires to the 70 Amp double pole circuit
breaker.

5

UL approved wire nuts are included with installation kit.

YOUR GUARDIAN

®

GENERATOR READY KIT 

IS NOW INSTALLED!

Connection of Emergency Circuits

13a

Install 70 AMP Circuit Breaker

14

Connection of Emergency Circuits

13b

Summary of Contents for 1276-1

Page 1: ...the Guardian Home Standby Generator or the Owner s Manual furnished with the Guardian Ultra Source Portable Generator you may purchase in the future Please review the installation procedure again at t...

Page 2: ...Generator for emergency power now Later install your Standby for automatic emergency power 100 AMP automatic transfer switch with built in load center 30ft and 2ft pre wired conduits 5ft power cord an...

Page 3: ...INSTALLATION DRAWING AUTOMATIC TRANSFER SWITCH CONNECTED TO THE EXTERNAL CONNECTION BOX Installation Guide...

Page 4: ...y possible circumstance that might involve a hazard The warnings in this manual and on tags and decals affixed to the unit are therefore not all inclusive If you use a procedure work method or operati...

Page 5: ...N TO THE HOME S MAIN DISTRIBUTION PANEL 12 UL LISTED WIRE NUTS not shown TOOLS REQUIRED Drill drill bits hole saw type and length will be determined by the materials you will be drilling and cutting o...

Page 6: ...Let the engine run for a minute or two at no load to stabilize the internal temperatures 3 Turn off the generator 4 Turn OFF the utility power supply to the transfer switch using the means provided s...

Page 7: ...of main distribution panel The automatic transfer switch can be located to the left or right of main distribution panel Hold transfer switch against the mounting surface Level the transfer switch and...

Page 8: ...f a power failure Wire nut the black wire to the matching circuit lead wire from the emergency circuit breaker from load center in the transfer switch All circuit wires are color coded and labeled for...

Page 9: ...on to enter beyond the clamp to the inside of the box TIghten clamp securely Attach ground wire green to the bottom of the box using the supplied ground screw and pre drilled hole Connect red black an...

Page 10: ...and length of the generator mounting pad 48 L x 24 W 3 Lay black poly film to cover the area 4 Fill the area to ground level with pea gravel or crushed stone 5 Drive an 8 foot grounding rod into the g...