Section 3.  Description and Principles of Operation (cont.) 

 

CAUTION:

   

The green ground wire and test connector 

must be connected to the breaker before the power is 
turned on. 

 

OPERATION OF TEST CABINET:

 (Circuit breaker must be 

out of its cubicle) 

 

1.  Make sure both CONTROL POWER switches are in the 

“OFF” position. 

2.  Connect the green ground wire to the breaker frame. 

3. Plug the TEST CONNECTOR into the breaker 

secondary disconnect.  Use only the secondary 

disconnect on the top left of the breaker (viewed 

from the front of the breaker). Make sure the TEST 

CONNECTOR is fully engaged into the breaker 

secondary disconnect. 

4.  Turn the CLOSE & TRIP power switch to the “ON” 

position. The trip power and close power indicating 

lights should be illuminated. If any of the indicating 

lights fail to illuminate, check the appropriate control 

power fuse(s) located at top. If the fuses are not 
blown, check the lamp in the indicating light 
assembly. 

5.  Move the CHARGE MOTOR CONTROL POWER switch 

to the “ON” position to charge the closing springs. 
The charge control power indicating light should be 
lit.  The charge switch can remain in the “ON” position 
during testing. 

6.  The circuit breaker close and trip circuits can now be 

exercised by operating the CLOSE and OPEN 

switches on the test cabinet. Operation of the 
breaker auxiliary switch can be verified by observing 
the RED and GREEN indicating lights on the test 
cabinet. When breaker contains a command close 
coil (ccc) the operations as follows. For closing rotate 

and hold the close switch to the right.  Push the 

green button on the breaker. This button is located 

between the Close & Trip buttons when a command 
close coil is present. 

7.  Undervoltage coil 1 operation (when equipped) can 

be verified by rotating UV1 switch to the left. 

8.  Shunt trip coil 2 operation (when equipped) can be 

verified by rotating the TRIP2 / UV2 switch to the left. 

9.  Undervoltage coil 2 operation (when equipped) can 

be verified by rotating switch from right position to 

center.  When the breaker is equipped with UV2, the 
TRIP2 / UV2 switch must be turned to right position 

before closing breaker or the breaker will go trip free.  

10.  When breaker testing is complete, turn the CONTROL 

POWER and CHARGE switches to the “OFF” position. 

Pull the TEST CONNECTOR out of the breaker 
secondary disconnect. Remove the green ground 

wire from the breaker frame. 

11.  Discharge the charging spring before attempting to 

install the breaker into its cubicle. 

 
 
 

 
 
 
 

 
 
 
 
 

 

 

Section 4.  Installation 

 

 

 

The test cabinet should be installed on the wall at a 

location where maintenance and testing of the breaker 
can be conveniently done. 

 

Conduits may be installed for cables to supply control 

power for testing. Two 1-inch diameter holes are located 
on the left side to accommodate wiring. Refer to the 
wiring diagram in Figure 2 for control power connections 
and jumper positions. 

Section 5.  Maintenance 

 

 

 

 

Aside from keeping the unit clean and dry, the most 
important thing is to return the clamp to the cabinet area 
when not connected to a breaker.  

Summary of Contents for EntelliGuard G

Page 1: ...DEH41480 Test Cabinet Inspection Box for Testing Accessories on Manually and Electrically Operated EntelliGuard G Low Voltage Circuit Breakers Instructions 1...

Page 2: ...Section 1 Introduction 1 1 Introduction 6 1 2 Safety 6 1 3 Maintenance 6 Section 2 Receiving Handling Storage 2 1 Receiving 7 2 2 Handling 7 2 3 Storage 7 Section 3 Description Principals of Operatio...

Page 3: ...2 Test Cabinet Schematic Diagrams 10 3 Test Cabinet Internal Wiring Diagram 11 THESE INSTRUCTIONS ARE INTENDED FOR USE BY QUALIFIED PERSONNEL FOR INSTRUCTION AND MAINTENANCE PURPOSES REPRODUCTION IN...

Page 4: ...ation NFPA 70B Electrical Equipment Maintenance must be closely studied and followed During actual work supervision should audit practices to assure conformance 1 3 Maintenance Excellent maintenance i...

Page 5: ...led immediately with the transportation company and the nearest General Electric Sales Office should be notified It is expected that due care will be exercised during the unpacking and installation of...

Page 6: ...d closing and charging the breaker and control power switch all located on the front of the cabinet Separate fuse holders and control power indicating lights are provided for the charge close and trip...

Page 7: ...e test cabinet When breaker contains a command close coil ccc the operations as follows For closing rotate and hold the close switch to the right Push the green button on the breaker This button is lo...

Page 8: ...EntelliGuard GTM Breaker Test Cabinet Figure 2 Test Cabinet Schematic Diagrams 8...

Page 9: ...EntelliGuard GTM Breaker Test Cabinet Control Power Connection Figure 3 Test Cabinet Internal Wiring Diagram 9...

Page 10: ...uld further information be desired or should particular problems arise which are not covered sufficiently for the purchaser s purposes the matter should be referred to the General Electric Company GE...

Reviews: