Section 3.  Description and Principles of Operation 

 

The test cabinet, catalog no. GTC250 (Fig.1) is used to 

operate an EntelliGuard G

TM

 Drawout low voltage power 

circuit breaker that has been removed from the metal-

enclosed equipment.  It provides a convenient means of 
accessing the electrical close and trip circuits of the 

breaker during maintenance and inspection procedures.  

Control voltages must match the rating of charge, close, 

and trip circuits on the breaker. 

 

This unit is designed to be wall or cabinet mounted. It has 

a test connector (with green ground wire), a 10-foot wire 

bundle, switches for opening and closing and charging 

the breaker, and control power switch, all located on the 
front of the cabinet. 

 

Separate fuse holders and control power indicating lights 

are provided for the charge, close, and trip circuits. Lights 

are also provided for breaker open and close indication. 
Inside the unit is a terminal block for connecting the 

control power source(s) to the test cabinet. Four holes are 

provided on the back of the test cabinet for mounting 

using 3/8-inch hardware (mounting hardware is not 

included).  

 

 

1.   Control power input holes 

2.   Terminal block for control power (inside) 

3.   Clamp for test connector cable 

4.   Fuse holders 

5.   Control power indicating lights 

6.   CLOSE/OPEN push button switches 

7.   Close & Trip control power OFF / ON switch 

8.   Green/Red indicating lights 

9.   Charging motor control power OFF / ON switch                              

  

 

 

Figure. 1.  EntelliGuard G

TM

 Test Cabinet

 

 

 
 

Summary of Contents for EntelliGuard G

Page 1: ...DEH41480 Test Cabinet Inspection Box for Testing Accessories on Manually and Electrically Operated EntelliGuard G Low Voltage Circuit Breakers Instructions 1...

Page 2: ...Section 1 Introduction 1 1 Introduction 6 1 2 Safety 6 1 3 Maintenance 6 Section 2 Receiving Handling Storage 2 1 Receiving 7 2 2 Handling 7 2 3 Storage 7 Section 3 Description Principals of Operatio...

Page 3: ...2 Test Cabinet Schematic Diagrams 10 3 Test Cabinet Internal Wiring Diagram 11 THESE INSTRUCTIONS ARE INTENDED FOR USE BY QUALIFIED PERSONNEL FOR INSTRUCTION AND MAINTENANCE PURPOSES REPRODUCTION IN...

Page 4: ...ation NFPA 70B Electrical Equipment Maintenance must be closely studied and followed During actual work supervision should audit practices to assure conformance 1 3 Maintenance Excellent maintenance i...

Page 5: ...led immediately with the transportation company and the nearest General Electric Sales Office should be notified It is expected that due care will be exercised during the unpacking and installation of...

Page 6: ...d closing and charging the breaker and control power switch all located on the front of the cabinet Separate fuse holders and control power indicating lights are provided for the charge close and trip...

Page 7: ...e test cabinet When breaker contains a command close coil ccc the operations as follows For closing rotate and hold the close switch to the right Push the green button on the breaker This button is lo...

Page 8: ...EntelliGuard GTM Breaker Test Cabinet Figure 2 Test Cabinet Schematic Diagrams 8...

Page 9: ...EntelliGuard GTM Breaker Test Cabinet Control Power Connection Figure 3 Test Cabinet Internal Wiring Diagram 9...

Page 10: ...uld further information be desired or should particular problems arise which are not covered sufficiently for the purchaser s purposes the matter should be referred to the General Electric Company GE...

Reviews: