4 M
AINTENANCE
Maintenance measures recommended in EN54-14 must be adopted.
Maintenance to be performed by the installer or the maintenance company
Quarterly
Inspect the entries in the on-site register and the records of the control panel.
Implement the appropriate corrective action.
Check all battery connections and the battery voltages.
In every zone, check the alarm, faults and all auxiliary functions of the control and
signalling equipment.
Visually inspect the control and signalling equipment to detect any possible increase
in humidity and/or any other type of deterioration.
Check if there has been any structural alteration to the site that may affect the
functioning of the detectors, manual call points or sounders. If so, take the
appropriate action.
Any failure must be noted down in the on-site register book and the corrective action
taken as soon as possible.
Yearly
Place the control panel in “Test” and check the configuration of the system. Check
that all the detectors and manual call points work according to the manufacturer’s
specifications and programmed requirements.
Visually inspect all the equipment connections and make sure that they are securely
fastened, that they have not been damaged and that they are appropriately protected.
Examine and test all batteries.
Any defect must be noted down in the on-site register and the corrective action taken
as soon as possible
Summary of Contents for ARITECH FP400 Series
Page 25: ...FP400 Series Installation Manual 25 ...
Page 26: ...26 FP400 Series Installation Manual ...
Page 27: ...FP400 Series Installation Manual 27 ...
Page 28: ... 1050086 ...