Installing New Atlas Motor Kits

  

12

Tighten the two shoulder bolts on the bottom of the deck plate.

13

Check belt alignment and tension. Readjust, if necessary.

14

Connect the motor wires in the junction box.

15

Ensure that the voltage on the motor is set correctly by checking the motor power select switch 
in front of the motor. Adjust, if necessary. Refer to 

Figure 3

.

Figure 3: Atlas Pump - Motor Select Switch.

Motor power select 
switch - shown in low 
voltage setting (110 volt 
nominal)

Verifying Performance 

1

Verify completion of the reassembly.

2

Connect the amp probe to a power leg of the motor.

3

Operate the unit and record the initial readings.

Parameter

Reading

Full Flow Amperage

Bypass Amperage

Bypass Voltage

Note: To maximize the flowrate, the pumping unit bypass valve spring preload will need to be 

adjusted. The maximum allowable load on the new motor is 5.5 amps at 220 volts 

(nominal) and 11 amps at 110 volts nominal.

 

Summary of Contents for Atlas M06699K Series

Page 1: ...99K002 Atlas Motor Kit 1 HP 50HZ 1PH Required Reading Before installing a kit the installer must read understand and follow This manual NFPA 30A The Automotive and Marine Service Station Code NFPA 70...

Page 2: ...99K001 Part Number Description Quantity per Kit R14213 32 Motor 1 HP 60 Hz 1 PH 1 R06711 52 V Belt 4L290 1 R18900 27 Pulley A Belt 2 50 PD 1 Atlas Motor Parts List for M06699K002 Part Number Descripti...

Page 3: ...ual Read understand and follow this manual and any other labels or related materials supplied with this equipment If you do not understand a procedure call a Gasboy Authorized Service Contractor or ca...

Page 4: ...handling equipment Do not place any equipment in mouth This area contains a chemical known to the State of California to cause cancer WARNING This area contains a chemical known to the State of Califo...

Page 5: ...oving the Old Motor 1 Disconnect motor wires in the junction box Mark wires in junction box so that you can be sure of connecting the new motor correctly 2 Remove the belt 3 Disconnect motor conduit a...

Page 6: ...te flange 6 Replace the rubber mounts cupped washers and washers and the shoulder bolts in the slots on the bottom of the deck plate and thread the shoulder bolts into the clinch nuts in the bottom fr...

Page 7: ...r Adjust if necessary Refer to Figure 3 Figure 3 Atlas Pump Motor Select Switch Motor power select switch shown in low voltage setting 110 volt nominal Verifying Performance 1 Verify completion of the...

Page 8: ...s Screw 2 If the amperage from the initial test is low turn the adjustment screw clockwise and increase the preload and thus the flowrate and motor load Note If the initial bypass voltage is below 205...

Reviews: