13-25-639 v00 Page 37
8.2
Putting a decommissioned compressor back into operation
Before commissioning the compressor all the electrical and electronic components and units should be checked for the
ingress of water or condensation.
If the electronic control system was removed during shut down, it must be re-installed.
Then proceed as described in Section 8.1 'First commissioning'.
8.3
Display of the compressor controller
Fig. 15
1. Touchscreen Display
2. Start push-button [ I ]
3. Stop push-button [ O ]
4. Emergency stop
NOTICE
Only for L90RS-L132RS: If the compressor has been in storage for a substantial period of time (up to
2 years), switch the main power supply switch on (ON) at least one (1) hour prior to commissioning. This
ensures the operability of the capacitors and prevents any damage from occurring.
If the compressor has been in storage for longer than 2 years, please contact an authorized Gardner
Denver Distributor prior to start-up.