HF-7-600 Page 4
SECTION 2
INSTALLATION
LOCATION
If possible, install the blower in a well lit, clean, dry place with plenty of room for inspection and
maintenance.
FOUNDATIONS
For permanent installations we recommend concrete foundations be provided, and the equipment should
be grouted to the concrete. It is necessary that a suitable base be used, such as a steel combination
base under blower and motor, or a separate sole plate under each. Before grouting, equipment must be
leveled, free of all strains, and anchored so no movement will occur during setting of grout. After grout
has completely hardened, a recheck is necessary to compensate for shrinkage, etc. If required, add
shims under blower feet after final tightening of foundation anchor bolts to remove strain from the blower
housing. Where jack screws or wedges are used during grouting, they must be backed off or removed
before final tightening of anchor bolts.
Where a concrete foundation is not feasible, care must be taken to insure that equipment is firmly
anchored to adequate structural members.
MOUNTING CONFIGURATIONS
The blower flex-mounting design enables horizontal and vertical mounting configurations with top or
bottom hand, right or left hand shaft positioning. The units are discharge timed allowing rotation in only
one direction (refer to
FIGURE 2-1
).
FIGURE 2-1– BLOWER MOUNTING CONFIGURATIONS