Instruction Manual
Top & Bottom Loading Arms
E2110, E2112, E2022, E2025
E2033, E2304, E2573, E2123,
E2313, E2121
- 8 -
the support bearing bracket. Ensure that the slew axis of the boom is in a vertical
position. (previous note only applies when bracket or stand post is supplied)
The inlet flange attachment bolts and nuts are not included in the scope of
delivery. Select adequate bolts and nuts which are suitable for the weight and the
bending moment. Use all attachment provisions.
Connect the flanges and install gaskets at the flanges.
Remove the transport locks from the loading arm and spring cylinder (See Figure
5 below).
Figure 5
Install components supplied separately (such as overfill device, parallel guide,
hoses, couplers etc., if applicable). Refer to the loading arm drawing for more
information.
Once installed, move the loading arm and verify that it will hold its position. If the
loading arm slews about its axis, ensure that the mounting flange is level. If the
arm is not properly balanced, adjust the balance of the spring cylinder (refer to
the spring cylinder adjustment manual for procedure). Although all components
have been adjusted to proper values by the factory, minor adjustments may be
required.
Caution
If the loading arm is inadequately
balanced or moves on its own it may hit
persons nearby causing injury.
Adjust arm and mounting flange to suit.
Ensure not to enclose any objects in the system (e. g. tools or bolts). Clean all
tubes before final installation.
The operator of the system is responsible for grounding the system and
protecting it from lightning.
Only persons with the required training and qualification should connect and
maintain the electrical, pneumatic or hydraulic systems. Connect these systems
according to the accompanying diagrams and data sheets.