Installation

The devices are attached to a suitable structure by use of the top anchor point. This allows for firm 

connection without compromising the weatherproofing of the enclosure.

The LHD-INT unit has two cable glands, the left hand gland facilitates the entry of the digital linear

heat cable so that it can be terminated in the LHD-INT as shown in diagram 3. The right hand cable 

gland allows for a 4 core cable to enter the LHD-INT unit to terminate the 24Vdc power and the 

zone interface. The LHD-INT can be connected directly to a conventional fire panel zone and 

auxiliary power output or to an input interface from an addressable fire detection panel. 

The termination into the INT-EOL is simply one core of the digital linear heat cable into each 

terminal, there is no need to observe any polarity. 

PLEASE NOTE neither the LHD_INT OR LHD_EOL will operate correctly without both being 

installed on the digital linear heat cable.

Diagram 3 – LHD-INT Cable termination

Fire and EOL resistors are dependent on the fire alarm control equipment specification.

 

LHD-INT & LHD-EOL Installation Guide

Page 4

Rev.1.7 ©G2 Security Pty Ltd