In the following days after initial installation check the ground anchors are ‘as’ installed and check
guy rope tension. Re-tension the guy ropes if necessary. If re-tensioning was required then repeat
the check in the following days.
Higher level parts can only be checked visually whilst the tower is up, however if it is taken down
due to expected extreme weather then all items should be checked at this opportunity. At the very
least the tower should be taken down for a maintenance check within the first three months and
then every twelve months. The frequency of these checks will need to be altered depending on local
weather conditions experienced.