Franklin Fueling Systems UPP PIPING Installation Manual Download Page 12

10

NOTE:

 Both ends of the tape should be grounded during installation.

Ends of Tape Must be Grounded at Sumps

Earthing Rod

When using a detection tool, the near end of the detectable tape should be disconnected from the grounding 

point to allow the red cable from the transmitter to be connected to the tape and the black cable from the 

transmitter to be connected to the grounding point. The far end of the tape should remain grounded to give the 

highest signal strength and the earth spike should be as far away from the trace path as possible at a 90 degree 

angle.
Use the lowest frequency possible from the transmitter around 577 Hz or 8 kHz to eliminate coupling to other 

grounded cables. Use the receiver to follow the path of the tape to locate the buried pipe. Follow direction 

included with the receiver and transmitter for detecting buried pipe location.

PRESSURE TESTING

Following inspection, prior and subsequent to backfilling, a tightness test should be carried out by a competent 

person on each pipe run, chamber and sump to verify the integrity of joints and seals. This testing should meet 

the requirements of local officials and engineers and comply with local health and safety regulations. The 

following testing procedure is suggested for guidance only and should in no way override oil companies or local 

regulator’s requirements.

TESTING GUIDELINES 

Equipment:

•  Target test pressure should be 50% of scale on gauge, e.g. if the test pressure is 1 Bar  

(14.5 psi), use a 2 bar (29 psi) gauge.

•  Gauges should have serial numbers and be tested and certified every year.

•  Pressure testing equipment should have fitted a relief valve set at around 0.5 bar (7.25 psi) above the test 

pressure.

General Guidelines:

•  When applying pressure from gas cylinders, use suitable valves to ensure test pressure is not exceeded.

•  Apply pressure or vacuum slowly to minimise risks.

•  When you test primary pipe for tightness, the secondary should be open to atmosphere. 

•  Secondary Gemini® fittings should not be welded prior to testing primary to allow inspection of joints.

•  When you test secondary pipe for tightness, the primary should be open to atmosphere. (The exception is 

when you test the secondary pipe at a pressure higher than the recommended value in Table 5. When this 

is the case, pressurize the primary pipe to a pressure that is ≥ (Secondary Test Pressure - 1 bar).

•  Wipe each joint with soapy water to check for leaking.

 

WARNING:

 Follow all federal, state, and local laws governing the installation of this product and its associated 

systems. When no other regulations apply, follow NFPA codes 30, 30A, and 70 from the National Fire Protection 

Association. Failure to follow these codes could result in severe injury, death, serious property damage, and/or 

environmental contamination.

 

WARNING:

 To avoid explosion hazards, nitrogen or an inert gas from a pressure cylinder should be used in 

place of compressed air for tightness testing if fuel has been used to ballast underground storage tanks or if 

pipe-work has previously contained petroleum.

Summary of Contents for UPP PIPING

Page 1: ...UPP PIPING INSTALLATION GUIDE ...

Page 2: ...ETY 1 SITE PREPARATION 2 UNDERGROUND FUEL PIPE SYSTEMS 3 UNDERGROUND FUEL PIPE CONSTRUCTION 4 TRANSIT OFF LOADING AND STORAGE 5 STORAGE ON SITE 5 UNCOILING PIPE 6 CUTTING STRAPS 6 PIPE BURIAL GUIDELINES 7 PRESSURE TESTING 10 TESTING GUIDELINES 10 RECOMMENDED PIPE TEST PROCEDURE 11 ...

Page 3: ...ent is designed to be installed in areas where volatile liquids such as gasoline and diesel fuel are present Working in such a hazardous environment presents a risk of severe injury or death if you do not follow standard industry practices and the instructions in this manual Before you work with or install the equipment covered in this manual or any related equipment read this entire manual partic...

Page 4: ...ty guidelines given on the chemical containers themselves or on any accompanying literature WARNING Some installation of UPP products may occur in confined spaces where a lack of oxygen and a concentration of toxic vapors is likely to be experienced WARNING Such working conditions are dangerous and all local health and safety guidelines for working in such environments should be followed WARNING E...

Page 5: ...CLAMP A Electrofusion Entry Seal Clamps for PE sumps 303 CLAMP 1 304 CLAMP Properly sized hole saws for FEB or EIF entries Fiberglass Entry Boots FEB 075 Entry Seals use a hole saw HS3 58 92 mm 3 FEB 110 Entry Seals use a hole saw HS5 140 mm 5 FEB 125 Entry Seals use a hole saw HS5 140 mm 5 Electrofusion Entry Seals 303 Entry Seals use a hole saw HS3 102mm 4 304 Entry Seals use a hole saw HS5 140m...

Page 6: ...f the pipe is High Density Polyethylene HDPE grade PE100 that allows the use of electrofusion couplers and fittings to construct a variety of pipeline configurations HDPE PE100 has well proven resistance to stress cracking puncture scratch impact microbial and rodent attack The intermediate tie layer causes a permanent bond to occur between the polyethylene and the liner material The liner of UPP ...

Page 7: ...y wedges The bottom layer of pipes should be laid on timber battens at 1m 3ft centres to avoid any damage from sharp objects lying on the ground Pipe crates should be stored on clear level ground and should never be stacked more than three crates high Coils should be stored on firm level ground that has suitable protection for the bottom of the coil Primary pipe and UL double wall pipe can be stac...

Page 8: ... be release in an uncontrolled fashion Staking is required every 1m to hold coil in place during relaxation period Once a coil is completely uncoiled the far end of the coil must be secured to a stable anchor point Coil Weights RELAXINGAND ROUTING Staking coil Metal or wood stakes at least 1 2 meter in length and at least 30 mm x 30 mm are recommended for every 1 meter of coiled pipe Stakes should...

Page 9: ...prominent hook that can be partially removed when weight is placed on it bags of sand or pea gravel or use the hook end to your advantage when turning direction into a chamber or pump sump PIPE BURIAL GUIDELINES Recommended burial depth of UPP pipe is a minimum of 300 mm 12 All trenches should be sloped back towards the storage tanks The fall back slope for all pipework to the tank chambers should...

Page 10: ...any thermal expansion will be accounted for by following our guidelines for spacing backfilling and ensuring runs are snaked Pipes should be separated from each other by at least the diameter of the largest pipe If pipe runs cross they must be separated by at least as much backfill material as the diameter of the largest pipe or protected using at least 25mm 1 of expanded polystyrene NOTE If used ...

Page 11: ...t 5 Double Wall Pipe EN14125 40 32mm 1 63 50mm 1 75 63mm 2 110 90mm 3 125 110mm 4 0 5 m 1 ft 7 0 75 m 2 ft 6 0 9 m 3 ft 1 35 m 4 ft 5 1 65 m 5 ft 5 Single and Double Wall UL971 Pipe 63mm 2 90mm 3 63 50mm 1 75 63mm 2 110 90mm 3 125 110mm 4 1 m 3 ft 3 3 m 9 ft 10 1 m 3 ft 3 1 m 3 ft 3 4 m 13 ft 2 4 m 13 ft 2 PIPE DETECTORTAPE UPP Detectable tape is used to allow the piping location to be found after...

Page 12: ... 50 of scale on gauge e g if the test pressure is 1 Bar 14 5 psi use a 2 bar 29 psi gauge Gauges should have serial numbers and be tested and certified every year Pressure testing equipment should have fitted a relief valve set at around 0 5bar 7 25 psi above the test pressure General Guidelines When applying pressure from gas cylinders use suitable valves to ensure test pressure is not exceeded A...

Page 13: ...g set at 11bar 159 psig Conditioning Phase Fill the pipe work system to be tested with water making sure that any air relief valves are opened while filling the pipe work After filling the pipe work wait 1 hour for the temperature to stabilize Pressurize the system to 10 bar 145 psi and maintain this pressure for 30 minutes System pressure shall be maintained by means of refilling in order to comp...

Page 14: ...ressure inside primary pipe 1 bar Test Procedure Record Temperature and Pressure at start of each test time Condition and test the piping as follows 1 Pressurize the piping to 10 of test pressure hold pressure for 30 minutes and inspect for leakage or pressure drop 2 Increase pressure to 50 of test pressure and again inspect for leakage while holding pressure for 30 minutes 3 Increase pressure to ...

Page 15: ...lts on this Sump Inspection Register and have the fault s corrected at the time found You can download this form part number 408001011 from the FFS website at www franklinfueling com End user proprietary inspection check register logs or any form to record these inspections is acceptable ...

Page 16: ...408001016 r7 ...

Reviews: