CHAPTER 2: INSPECTION, TRANSPORT AND SITE HANDLING
2.1 INSPECTION
After receiving the unit, immediately check its integrity. The unit left the factory in perfect condition;
any eventual damage must be questioned to the carrier and recorded on the Delivery Note before it
is signed. Our firm must be informed, within 8 days, of the extent of the damage.
The Customer must prepare a written statement of any severe damage
.
2.2 LIFTING AND SITE HANDLING
The lifting is obtained by using a forklift: fork must be inserted in the base pallet, and care must be
taken in order that the fork does not hit the section base or panel (see the picture below).
To unload the unit with a crane, pass bars under the machine and attach the necessary cable or chain
lifting devices to the bar, ensuring that they are clamped firmly; protect the sides of the chiller with
boarding or material of a similar nature.
2.3 UNPACKING
When unpacking the unit pay attention not to damage the unit.
The package is made up by different materials: wood, paper, nylon etc.
It’s a good rule to keep them separately and deliver to the proper collecting centre in order to reduce
their environmental impact.
Lifting method with a crane Lifting method with a forklift
Protection boarding
Spacing bars
3m min