Hardware Installation 

12 

such as SO

2

, H

2

S, NO

2

, NH

3

 and Cl

2

, etc. The table below details the threshold value. 

 

Gas 

Average (mg/m³) 

Max (mg/m³) 

SO

2

 

0.2 

1.5 

H

2

0.006 

0.03 

NO

2

 

0.04 

0.15 

NH

3

 

0.05 

0.15 

Cl

2

 

0.01 

0.3 

Table 2-2 Environmental Requirements: Particles 

2.1.1.2

 

Temperature and Humidity 

Although  the  switch  is  designed  to  use  4  fans,  the  site  should  still  maintain  a  desirable 

temperature and humidity. High-humidity conditions can cause electrical resistance degradation or 

even electric leakage, degradation of mechanical properties and corrosion of internal components. 

Extreme low relative humidity may cause the insulation spacer to contract, making the fastening 

screw  insecure.  Furthermore,  in  dry  environments,  static  electricity  is  liable  to  be  produced  and 

cause harm to internal circuits. Temperature extremes can cause reduced reliability and premature 

aging of insulation materials, thus reducing the switch‟s working lifespan. In the hot summer, it is 

recommended  to  use  air-conditioners  to  cool  down  the  site.  And  the  cold  winter,  it  is 

recommenced to use heaters. 

 

The recommended temperature and humidity are shown below: 

Temperature: 

Relative humidity 

Long term condition 

Short term condition 

Long term condition 

Short term condition 

15 ~ 30°C 

0 ~ 50°C 

40 ~ 65% 

10 ~ 95% 

Table 2-3 Environmental Requirements: Temperature and Humidity 

Caution! 

A sample of ambient temperature and humidity should be taken at 1.5m above the floor and 

0.4m in front of the switch rack, with no protective panel covering the front and rear of the rack. 

Short  term  working  conditions  refer  to  a  maximum  of  48  hours  of  continued  operation  and  an 

annual cumulative total of less than 15 days. Formidable operation conditions refers to the ambient 

temperature and relative humidity value that may occur during an air-conditioning system failure, 

and normal operation conditions should be recovered within 5 hours. 

 

 

Summary of Contents for S9524-GS12M2

Page 1: ...S95xx Duak Stack Ethernet Switch Manual version 2 0 04 Firmware version 6 2 98 0 FoxGate 2012 Installation Guide...

Page 2: ...11 2 1 1 Environmental Requirements 11 2 1 2 Installation Notice 14 2 1 3 Security Warnings 14 2 2 INSTALLATION PREPARATION 15 2 2 1 Verify the Package Contents 15 2 2 2 Required Tools and Utilities 1...

Page 3: ...aces S9524 GS12M2 provides 12 1000Mb fiber ports 12 1000Mb Combo ports 1000Mb fiber SFP ports 1000Mb copper ports and 2 slots with the extended cards S9548 GS4M2 provides 44 fixed 1000Mb fiber ports 4...

Page 4: ...95xx series switches fully support DiffServ Module Users can specify a queue bandwidth on each port WDRR SP SWDRR scheduling is also supported S95xx series support the port trust Users can configure t...

Page 5: ...60HZ The max voltage range 90V 264V AC 47HZ 63HZ DC input 48V DC input 48V 60V DC 2 5A Output power supply of PoE Do not support Do not support The max Power Consumption 65W 65W Fan Support automatic...

Page 6: ...k Panel of S9524 GS12M2 Back Panel of S9548 GS4M2 is same with S9524 GS12M2 it supplies 2 interfaces for the extended card 1 interface with 48V DC power input and 1 interface with 220V AC power input...

Page 7: ...atus Description Green On port is at link state Off port is not at link state Blink Send or receive the data Table 1 5 SFP Port LEDs LED Status Description Left LED On SFP port is at link state Off SF...

Page 8: ...is at link state On Green Blink Port2 of M1 is receiving or sending the data Off Port2 of M1 is not at link state On Orange Port2 of M1 is not at link state but M1 is in place M2 1 On Green Port1 of M...

Page 9: ...um single mode fiber 70km SFP LH 120 L transceiver 9 125um single mode fiber 120km SFP GT SFP GT module 1000Base T SFP interface card module RJ 45 interface 1 4 6 M9000 2X M9000 2S M9000 2S Extended M...

Page 10: ...e 1 21 panel diagram of M9000 2X Figure 1 22 panel diagram of M9000 2S Figure 1 23 panel diagram of M9000 2S Back panel diagram of the switch with extended modules is shown in the following Figure 1 2...

Page 11: ...50 m 2000MHz km MMF 300m XFP LR transceiver 10GBase LR XFP single mode fiber transceiver 1310nm SMF 10km XFP ER transceiver 1550nm SMF 40km XFP ER 70 transceiver 1550nm SMF 70km SFP SFP LR transceive...

Page 12: ...avoid the sunlight perpendicular incidence Keep the switch away from heat sources and strong electromagnetic interference sources The switch must be mounted to a standard 19 rack or placed on a clean...

Page 13: ...y and premature aging of insulation materials thus reducing the switch s working lifespan In the hot summer it is recommended to use air conditioners to cool down the site And the cold winter it is re...

Page 14: ...ce All sources of interference whether from the device system itself or the outside environment will affect operations in various ways such as capacitive coupling inductive coupling electromagnetic ra...

Page 15: ...t the fiber bore when the switch is in operation Otherwise the laser may hurt your eyes Do not attempt to conduct the operations which can damage the switch or which can cause physical injury Do not i...

Page 16: ...ts inside 2 2 2 Required Tools and Utilities The required tools and utilities are shown below Cross screwdrivers Flat blade screwdriver ESD wrist strap Antistatic uniform Caution Users should prepare...

Page 17: ...the S95xx series to the rack with the screws provided Leave enough space around the switch for good air circulation Caution The brackets are used to fix the switch on the rack They can t serve as a be...

Page 18: ...ou feel the transceiver snap into place at the bottom of the line card Note the SFP transceiver is hot swappable Caution Do not stare directly at the 2 fiber bore in the SFP transceiver when the switc...

Page 19: ...sert SFP fiber transceiver 2 3 6 M9000 2S Extended module Installation S95xx series provide 10Gb slots The procedure for installing the M9000 2S module and the SFP 1Gb fiber transceiver is shown below...

Page 20: ...cator a lighted LED indicates that the link has been established otherwise the link is not ready and should be examined Caution Please verify the sign above the port to ensure using the other ports Co...

Page 21: ...specification for the detailed information Connection procedure is described as below 1 Insert DC power linker provided in the accessory kit into DC power source socket in the back panel of the switch...

Reviews: