Figure 6 - Laying First Layer of Blocks
BUILDING FIRE RING
WARNING: Failure to position the parts in
accordance with these diagrams or failure to
use only parts specifically approved with this
appliance may result in property damage or
personal injury.
1/8” Head Joint
Figure 7 - Head Joints
GAS LINE PLANNING
The supply line will need to run vertical through the
heat shield in the center of the fire ring up to where
you will connect it to the gas regulator using a 1/2"
flared flex line (not included). There is a 1" hole in
the heat shield for the gas line (See Figure 5).
Figure 5 - Gas Line Planning
1" Hole
Heat
Shield
1/2" Flare
Connector
1. Locate a flat even surface to build your fire
ring. See
Specifications
page 4 for sizing and
Minimum Clearances
page 5 when selecting a
location.
2. Use 8 blocks to build the first layer (See Figure
6). After laying out all blocks, using a level, verify
all the blocks are level. Shim if necessary.
FOR PROPANE/LP ONLY: On the first layer,
leave 1/8" head joints between blocks (see
Figure 7). Do not grout between blocks. This
will allow air space for gas to dissipate and
not pool in the event of a gas leak.