10 FOOT RULE

All flue gas outlet chimney terminations must 

extend a minimum of 3 feet in height above 

highest point where it passes through the roof 

and must be at least 2 feet above highest point 

of the roof that is within a horizontal distance 

of 10 feet (see Figure 17).

INSTALLATION

Continued

FINISHING FIREPLACE

Combustible  materials,  such  as  wallboard, 

gypsum board, sheet rock, drywall, plywood, 

etc. may make direct contact with sides and 

top around the fireplace face. It is important 

that combustible materials do not overlap face 

itself. Brick, glass, tile or other noncombustible 

materials may overlap front face provided they 

do not obstruct essential openings like louvered 

slots or any other opening. When overlapping 

with a noncombustible facing material, use only 

noncombustible mortar or adhesive.

24" Min.

24" Min.

18" 

Min.

Typ.

Figure 16 - Multiple Chase Installation

10'

2' Min.

10'

3' Min.

2' Min.

3' Min.

Level of 

Flue Gas 

Outlet

Figure 17 - 10 Foot Rule

 CAUTION: All gas piping 

and connections must be tested 

for leaks after the installation 

is completed. After ensuring 

that the gas valve is on, apply 

soap and water solution to all 

connections and joints. Bubbles 

forming show a leak. Correct 

all leaks at once. DO NOT USE 

AN OPEN FLAME FOR LEAK 

TESTING AND DO NOT OPER-

ATE ANY APPLIANCE IF A LEAK 

IS DETECTED. LEAK TESTING 

SHOULD BE DONE BY A QUALI-

FIED SERVICE PERSON.

 WARNING: Do not operate an 

unvented gas log set in this fire

-

place with the chimney removed.

If  you  install  a  decorative  gas  appliance 

(vented gas log), the decorative gas appliance 

must comply with the 

Standard for Decorative 

Gas Appliance for Installation in Solid Fuel 

Burning  Fireplaces, ANS  Z21.60  or  Z21.84 

and shall also be installed in accordance with 

the 

National Fuel Gas Code, ANSI Z223.1/

NFPA 54 latest edition

.

  WARNING:  If  fireplace  has 

been used for wood burning, 

firebox  and  chimney  must  be 

cleaned of soot, creosote and 

ashes  by  a  qualified  chimney 

cleaner. Creosote will ignite if 

heavily heated.

 WARNING: When using 

a decorative vented gas log, 

damper must be removed or 

permanently locked in the fully 

open position and glass doors 

must be in fully open position.

Summary of Contents for F48H(I)(R)A

Page 1: ...standards or for use with a vent free gas log heater approved to ANS Z21 11 2 standard This wood burning fireplace complies with UL127 CAN ULC S610 M87 standard as a FACTORYBUILTAPPLIANCE FOR CANADA...

Page 2: ...t part not manufac tured or approved by FMI PRODUCTS LLC in combination with a FMI PROD UCTS LLC fireplace system Proper installation is the most important step in ensuring safe and continuous operati...

Page 3: ...er Using Straps Provided Hearth Spacer Required for Combustible Floor 0 to Bottom 12 Min Each Side Hearth Extension 72 X 20 Outside Air Access Location 1 5 Airspace Back and Sides 2 Chimney Airspace C...

Page 4: ...at the level of the flue gas outlet see Figure 15 page 9 FRAMING 1 Frame the opening for the fireplace using the dimensions shown in Figures 1 and 2 2 If the fireplace is to be installed directly on...

Page 5: ...eal Gap Fireplace Front Ember Protector Fireplace Front Raised Hearth Fireplace Front Elevated Ember Protector Ember Protector Seal Gap Hearth Extension MANTELS A mantel may be installed if desired se...

Page 6: ...ipe sections are locked together When installing double wall snap lock chimney to gether it is important to assure joint between chimney sections is locked Check by pulling chimney upward after lockin...

Page 7: ...8 24 36 48 4 3 8 16 3 8 ELBOW SET ONLY 9 3 4 25 1 2 1 12 3 4 30 3 4 1 15 34 3 4 1 18 40 1 1 21 1 4 46 1 4 1 23 3 4 49 1 4 1 1 27 3 4 56 3 4 1 30 60 3 4 1 1 33 66 1 36 71 1 1 38 1 4 75 2 41 1 4 80 1 4...

Page 8: ...Screws or Staples Min of 8 Firestop Spacer Screws or Staples Min of 8 PENETRATING ROOF To maintain a 2 clearance to pipe on roof with a pitch a rectangular opening must be cut 1 Determine center point...

Page 9: ...inst open edge of flashing see Figure 14 Apply waterproof caulk around perimeter of collar to provide a proper seal Figure 14 Storm Collar Chimney Pipe Waterproof Caulk Storm Collar Flashing Terminati...

Page 10: ...ot Rule CAUTION All gas piping andconnectionsmustbetested for leaks after the installation is completed After ensuring that the gas valve is on apply soap and water solution to all connectionsandjoint...

Page 11: ...ide of the hearth Figure 20 then tilt the top of the panel toward the firebox surround Hearth Right Face Slot Figure 20 Slots for Firebrick Walls 3 Secure the firebrick wall using two of the side reta...

Page 12: ...lication When bricks are wet any excess grout mixture on bricks will easily wipe off 2 In a heavy duty mixing bucket add equal parts cement and sand Add enough water and mix together well using a powe...

Page 13: ...screen rod into rings at top of screen Attach one push on nut to end of rod before attaching last ring of screen 2 Insert the round end screen rod into hole on the left and right side of smoke shelf...

Page 14: ...ing that the gas valve is on apply soap and water solution to all connectionsandjoints Bubbles forming show a leak Correct all leaks at once DO NOT USE AN OPEN FLAME FOR LEAK TESTING AND DO NOT OPER A...

Page 15: ...32 concrete drill bit not provided 5 Place rail back on bricks and align holes Secure using 9 concrete screws provided with glass door kit 6 Secure retaining clips to top and bottom rails see Figure 3...

Page 16: ...y dry mill end lumber and large amounts of paper or cardboard boxes can create an excessively hot fire and should not be burned in this fireplace Always keep the fire well back from the doors and neve...

Page 17: ...hen operating damperdoor pleasebeawareof sharp edges and corners Open andclosedamperdoorslowlyto avoid injury WARNING Risk of fire Re placegratewithFMIPRODUCTS LLC model 109496 01 grate only This grat...

Page 18: ...ding Brick 42 50 Red 1 3 125634 01 Hearth Red 1 125634 02 Hearth Ivory 1 4 124646 01 Rear Top Red 1 124646 02 Rear Top Ivory 1 5 124648 01 Right Red 1 124648 02 Right Ivory 1 6 124650 01 Left Red 1 12...

Page 19: ...12DM 24 12DM 36 12DM 48 12DM 12 12HT 18 12HT 24 12HT 36 12HT and 48 12HT 30 OFFSET AND RETURN 30E 12DM and 30E 12HT OPTIONAL OUTSIDE AIR KIT FOR FLOOR INSTALLATION AK4F OPTIONAL OUTSIDE AIR KIT FOR SI...

Page 20: ...537 www fmiproducts com ACCESSORIES Continued SQUARE CHASE TOP TERMINATION STL 12D ROUND TOP TERMINATIONS RLT 12D AND RLT 12HT OPTIONAL HEARTH SPACER HS48 24 ROUND WOODNOOK DHR 24 ROOF FLASHING V6F 10...

Reviews: