Fig. 6A
SHEET 10 OF 12
ST EP 6
Attach the other end of the cable by lifting
the opposite side of the front cradle and
fastening with a 1/ 2" x 2" bolt and nylock
nut as shown in Fig. 6B. Torque to 60
ft/ lbs.
Fig. 6D
Fasten the side cables to the lower frame
clamps using 1/ 2" x 5" bolts and nylock nuts
as shown in Fig. 6C. Check front corner
posts for square and torque to 100 ft/ lbs.
Fig. 6B
The ball screw side cable is attached to the
upper clamp using a 1/ 2" x 2" bolt and
nylock nut. See Fig. 6D. The other side
cable is attached to the upper clamp using
a 1/ 2" x 2" bolt and nylock nut as shown in
Fig. 6E. Torque both bolts to 60 ft/ lbs.
Remove the cable holder and insert the front
cable into groove on the sheave. Re-attach
the cable holder and sheave to clamp. Wrap
the cable around sheave and attach to the
clamp with a 1/ 2" x 2" bolt and nylock nut.
See Fig. 6A. Torque to 60 ft/ lbs.
Fig. 6C
Fig. 6A
Fig. 6E
Fig. 6B
Fig. 6D
Fig. 6E
See Fig. 6C
1/ 2 x 2" bolt
Cable
holder
1/ 2 x 2" bolt
1/ 2 x 5" bolt, nut
and flat washers
1/ 2 x 2" bolt
1/ 2 x 2" bolt