Step 6: Please switch on all breakers of Line wires in load side. This system will start to provide power to the
load.
Support three-phase equipment
Step 1: Check the following requirements before commissioning:
Correct wire connection
Ensure all breakers in Line wires of load side are open and each Neutral wires of each unit are connected
together.
Step 2: Turn on all units and configure LCD program 28 as P1, P2 and P3 sequentially. And then shut down all
units.
NOET:
It’s necessary to turn off switch when setting LCD program. Otherwise, the setting cannot be
programmed.
Step 3: Turn on all units sequentially.
LCD display in L1-phase unit
LCD display in L2-phase unit
LCD display in L3-phase unit
Step 4: Switch on all AC breakers of Line wires in AC input. If AC connection is detected and three phases are
matched with unit setting, they will work normally. If the sequences are not matched, it won’t work in Line
mode. You must exchange the wires of P2 & P3 or exchange the setting of P2 & P3.
LCD display in L1-phase unit
LCD display in L2-phase unit
LCD display in L3-phase unit
Step 5: If there is no more fault alarm, the system to support 3-phase equipment is completely installed. Step
6: Please switch on all breakers of Line wires in load side. This system will start to provide power to the load.
Note 1: To avoid overload occurring, before turning on breakers in load side, it’s better to have whole system
in operation first.
Note 2: Transfer time for this operation exists. Power interruption may happen to critical devices, which cannot
bear transfer time.
9. Trouble shooting
Situation
Solution
Fault
Code
Fault Event Description
60
Current feedback into
the inverter is
detected.
1.
2.
3.
Restart the inverter.
Check if L/N cables are not connected reversely in all inverters. For
parallel system in single phase, make sure the sharing cables are
connected in all inverters.
For supporting three-phase system, make sure the sharing cables are
connected in the inverters in the same phase, and disconnected in the
inverters in different phases.
4.
If the problem remains, please contact your installer.