16
PRIOR TO APPLICATION
1. Operator should familiarize themselves with the area to be seeded and develop a plan to
ensure uniform application.
2. Develop a plan for communication between operator and driver of the carrying or towing
vehicle to signal for start, stop, turn, etc. through the use of the signal horn.
3. Operator takes up position on the platform. From this point, application will be controlled by
the use of the clutch, valve, discharge assembly, and throttle.
DISCHARGE NOZZLE SELECTION
Nozzles are stored in the tool box. This HydroSeeder® is equipped with three nozzles – one long
distance and two fan nozzles. The following chart tabulates the approximate distance, width, and
discharge time of the nozzles when used with the platform option. When using the base unit, these
factors will vary according to the type and length of hose being used.
Nozzle
Distance (A)
Width (B)
Discharge Time
Long Distance
Up to 70 ft (21 m)
-
12 min
Narrow Fan
Up to 45 ft (14 m)
10 ft (3 m)
8 min
Wide Fan
Up to 35 ft (10 m)
20 ft (6 m)
8 min
A
B
Figure 4 – Discharge Nozzle
Spray Pattern
Summary of Contents for T30 HydroSeeder MO