37
Check visually that AASS transformer, main circuit breaker (if present) and UPS (if present)
are in general good conditions and that there are no hits, bumps or any visible damages
caused by transportation
□
Check that AASS transformer, main circuit breaker (if present) and UPS (if present) are prop-
erly fixed to the cabinet
□
Check visually that all the devices, such as circuit breakers, relays, terminal strip, etc.. of the
auxiliary board, are properly fixed and in general good conditions
□
Check that all the cables of the auxiliary board are firmly connected to their terminals.
□
Check the correct connection to the grounding grid
□
Verify that the value set in the thermostat of the Auxiliary Services Compartment are in accor-
dance with the specifications. Standard Value 35ºC
□
Check that all fuse holders (inverter string and LV device protection) include fuses and ensure
electrical continuity
□
Check that all the string input fuses bases are properly connected and closed.
□
Check the phase sequence of every incoming line from inverter is correct
□
7 - Finalizing the installation