Triangle Tube’s ProtoNode Startup Guide
Page 17 of 40
ProtoCessor
1991 Tarob Court Milpitas, California 95035 USA
Web
Figure 11: Connection from ProtoNode to RS-485 Field Network
BMS RS-485
Wiring
ProtoNode
Pin #
Pin
Assignment
RS-485 +
Pin 1
RS-485 +
RS-485 -
Pin 2
RS-485 -
-
Pin 3
RS-485 GND
+
-
G
Figure 12: RS-485 EOL Switch
End-of-Line Switch
3.4 LonWorks (FPC-N35): Wiring Field Port to LonWorks Network
Figure 13: LonWorks Terminal
•
Connect the BACnet MS/TP or Metasys N2 RS-485 network wires to the 3-pin RS-485 connector on
ProtoNode FPC-N34 as shown below in
Figure 11
.
•
See
Section 4
for information on connecting to BACnet/IP network.
•
If the ProtoNode is the last device on the BACnet MS/TP or Metasys N2 trunk, then the End-Of-
Line Termination Switch needs to be enabled (
Figure 12
). It is disabled by default.
•
Connect ProtoNode to the field network with the LonWorks terminal using a twisted pair non-shielded
cable. LonWorks has no polarity.
3.3 BACnet MS/TP or Metasys N2 (FPC-N34): Wiring Field Port to RS-485 Network