General:  

1.  If not installed correctly by qualified personnel, the brewer will not operate properly, and damage may result. 
2.  Utilize only qualified beverage equipment service technicians for service and installation. 
3.  Always have an empty dispenser under spray head of all coffee brewing equipment-including when at idle  
4.  Damages resulting from improper installation are not covered by the warranty, and will void the warranty. 
  Below are the key points to consider before installation: 

 

Electrical:  

1.  All CBS_Series brewers require 

an electrical ground wire

.  Installation without grounding is dangerous. 

2.  Note Equipotentiality Terminal, if present, 

(To identify the terminals which, when connected together, bring the various parts 

of equipment or of a system to the same potential, not necessarily being the earth (ground) potential, e.g. for local bonding.)

 

3.  Verify voltages, polarity, circuits, and circuit breaker access before attaching equipment. 
4.  Brewers in this series wire differently in regard to a neutral wire.  Review the wire diagrams. 
5.  The electrical diagram is located in the User’s Guide and online at www.fetco.com. 
6.  Make sure of the tight grounding of the equipment and use the external ground bolt. 
7.  The installation must comply with applicable federal, state, and local codes having jurisdiction at your location.  

Check with your local inspectors to determine what codes will apply. 

See wiring diagrams for connections 

 

Plumbing:  

1.  North America: All installations must comply with applicable federal, state, or local plumbing codes. 
2.  All Others:  The water and waste piping and connections shall comply with the International Plumbing Code 2003, 

International Code Council (ICC), or to the Uniform Plumbing Code 2003 (IAPMO). 

3.  Use an inline water filter for all beverage equipment.  A finishing carbon filter is preferred  
4.  Install the filter unit after a water shutoff valve and in a position to facilitate filter replacement. 
5.  The water line and newly installed filter cartage must be flushed thoroughly prior to connecting it to the brewer to 

prevent debris from contaminating the machine. 

6.  Verify that the water line will provide a flow rate of at least 1½gpm/(5.7lpm) per minute and the water pressure is 

between 20-75 psig (138-517kPa) before making any connections. 

7.  Hand tighten the factory fitting when connecting the incoming water line. This will reduce stress on the internal 

connections and reduce the possibility of leaks developing after the install has been completed 

8.  Install a backflow prevention device.  Most municipalities require a recognized backflow preventer.   
9.  Usable on all hot beverage and cold beverage equipment is a WATTS® SD-2 or SD-3.   
10. 

WATTS spring loaded double check valve models are accepted by most zoning authorities. 

   

The check valve should be as close to the water supply inlet of the beverage equipment as possible.  

 

Tank Drain 

The water tank must be drained before maintenance procedures, and when the unit is to be relocated or shipped 

 

1. Disconnect power and water to unit. DANGER: Insure that all utility connections to the brewer are broken. 
2. Move the unit near a sink or obtain a container large enough to hold four gallons of water.   

Note:  the hot water tank may hold more than four gallons. 

3. Remove the front panel and tank cover and allow the tank to cool to a safe temperature 
4. The tank drain line and clamp are located inside-under the hot water tank.  Pinch the drain line clamp to close 
5. Locate the fill valve against the back wall, using pliers, loosen the hose clamp and move it back over the tube. 

Note Do not loosen the hose clamp to the bottom of the hot water tank  

6. Crimp the tube an inch or two away from the drain plug to prevent water from flowing and pull it off the valve.  
7. Pull the tube end out of the brewer and position over sink or bucket. 
8. Release the crimped tube and hose clamp and allow the water to flow into the sink or container. 
9. Multiple buckets may be needed during the draining, see tank volumes below. 
10.  NOTE: Never plumb a water line into a drain. 

 

 
 
 
 
 
 
 

Summary of Contents for CBS-1221

Page 1: ...2 2 5 liter 3 liter and 3 8 liter air pots 1 9L server Value priced Self cleaning spray head patented for mineralization resistance E1221US 1X117 KM001 FETCO CBS 1221 brewer Gourmet plastic brew bask...

Page 2: ...4 minute brew time 2 0 minute drip delay all recipes Brew Process parameters are user controllable for Brew Volume Brew Time Prewet Percent and Prewet Delay Drip Delay Weights and Capacities Dispenser...

Page 3: ...er Programming There are 7 menu groups A F plus EXIT G See the following pages for the batch parameter definitions and all settings for the brewer TO ENTER PROGAMMING 1 Turn brewer OFF from power swit...

Page 4: ...72 PASTE To F10 Error Log F11 Erase Error Log F12 Service Phone The A menus A1 3 correspond to batch buttons 1 3 on the touch panel Access the A menus to PROGRAM make changes to individual menu recipe...

Page 5: ...or off Batches may be individually enabled rewritten or deactivated A21 Batch Volume 2 20liters 0 58gal 0 95 to 3 25L 0 25 to 0 85 gal 0 05L 0 01G Unit software is in liters converts to gallon A22 Br...

Page 6: ...2 5000 1524 194 202 4 90 94 7 5500 1676 193 201 5 89 94 2 6000 1829 192 200 6 89 93 6 6500 1981 191 199 6 88 93 1 7000 2134 190 198 7 87 92 6 7500 2286 188 197 8 86 92 1 8000 2438 187 196 9 86 91 6 85...

Page 7: ...r under brew basket Single series displays right side only Left Valve display is only for twin side brewer D9 LCD Brightness Brightness 90 20 100 5 Adjust LCD screen brightness only Not for LEDs under...

Page 8: ...l The software sets equipment to brewer defaults SETTING F3 4 When loading from USB Reprograms settings SETTING E7 5 When restoring defaults Reloads to defaults SETTING E8 F SERVICE MENU Software Code...

Page 9: ...r the brewer to reach operating temperature ERROR CODES DO NOT CLEAR ERROR CODES UNTIL ERROR IS IDENTIFIED AND OR CORRECTED Contact specialized personnel for error codes Code Description Possible Caus...

Page 10: ...5 Dry the face of the touch pad before turning on power 6 Do not electrically energize this equipment or attempt operation without all covers in place and all screws fastened 7 Unplug machine before...

Page 11: ...Install the filter unit after a water shutoff valve and in a position to facilitate filter replacement 5 The water line and newly installed filter cartage must be flushed thoroughly prior to connectin...

Page 12: ...with the specified cord only from the manufacturer in order to avoid a hazard 8 Review the dimensions for the unit and verify that it will fit properly in the space intended for it Verify that the co...

Page 13: ...ET SHORT SILICONE LEVEL AND TEMP PROBE 9 1 1112 00002 00 PROBE WELDMENT WATER LEVEL 2 25 LONG 10 1 1102 00161 00 PROBE ASSEMBLY TEMP AND LLC 8 LONG 11 1 1023 00362 00 FITTING VENT ELBOW 375 X 375 SELF...

Page 14: ...Go to fetco com for the latest versions of all information Page 14 User Guide Operator instructions P194Re0 November 2020...

Page 15: ...RETROFIT 16 2 1 1102 00479 00 ASSEMBLY CASCADE SPRAY DOME NEXT GEN BLUE 16 3 1 1023 00342 00 QUICK CONNECT CLIP 16 4 1 1057 00076 00 VALVE ASSEMBLY COMPLETE NG DELTROL 17 1 1024 00063 00 O RING 3 15...

Page 16: ...00 SCREW 1 4 20 X 5 FL HD PH W NYLN 4 1 1009 00006 00 WIRE BASKET 5 1 1102 00064 00 HANDLE W MAGNET ASY BLACK Optional colored handle 1102 00065 00 HANDLE W MAGNET ASY RED Optional colored handle 1102...

Page 17: ...Go to fetco com for the latest versions of all information Page 17 User Guide Operator instructions P194Re0 November 2020 Wiring Diagram...

Page 18: ...End of section notes N...

Reviews: