Festo — MSE6-C2M — 2022-08b
Commissioning
DIL switch 3
Setting IP addressing
1
2
3
4
5
6
7
8
DIL 3.1 … 3.8: OFF
Dynamic/saved addressing.
All DIL switches in the OFF position, factory setting.
When switched on, the energy efficiency module receives a
dynamic or stored IP address via ‘DHCP/BOOTP’.
1
2
3
4
5
6
7
8
DIL 3.8: OFF 2
7
= 128
Fixed addressing.
The host-ID of the IP address, 4th octet, is binary-coded with DIL
switch 3.1 … 3.8. Permissible value range: 1 … 254.
Example:
2
1
+ 2
2
+ 2
4
+ 2
6
= 2+ 4 + 16 + 64 = 86 host-ID
Set IP address: 192.168.1.86
DIL 3.7: ON 2
6
= 64
DIL 3.6: OFF 2
5
= 32
DIL 3.5: ON 2
4
= 16
DIL 3.4: OFF 2
3
= 8
DIL 3.3: ON 2
2
= 4
DIL 3.2: ON 2
1
= 2
DIL 3.1: OFF 2
0
= 1
1
2
3
4
5
6
7
8
DIL 3.1 … 3.8: ON
Reset all IP parameters to factory settings.
All DIL switches in ON position.
All IP parameters of the energy efficiency module are reset to the
factory settings when device is switched on.
Tab. 38: Set IP addressing, DIL switch 3
8.3.4
Commissioning and configuration
Commissioning and configuration of the bus node depend on the higher-order control. In the following
section the basic procedure for commissioning and configuration with the ‘Festo Maintenance Tool,
CPX-FMT’ software is explained.
The following steps provide an example for the use of an Allen-Bradley controller and the ‘Rockwell
Studio 5000’ controller software, Version 24, and the ‘Festo Maintenance Tool, CPX-FMT’ software in
English. Detailed information is provided in the documentation for the higher-order controller and the
controller software.
Switching on the power supply
If the control and network devices have separate power supplies, they must be switched in the
following sequence:
1. Switch on the power supply of the energy efficiency module.
2. Switch on the power supply for the controller.